Contract: PINNACLE CONSTRUCTION AND DEVELOPMENT CORP.
Primary Recipient
PINNACLE CONSTRUCTION AND DEVELOPMENT CORP.
Amount
$3,044,498.99
Award Date
4/07/2009
Administering Agency
CDFA Number
CDFA Program Title
Description
The primary objective of the work under this project is restoration and modernization of the existing facilities for improved efficiency and morale. A total of 375 days has been allocated for the completion of this project - 90 days for the design and 27
Recipients Connected to Award
Recipient | Role | Amount |
---|---|---|
PINNACLE CONSTRUCTION AND DEVELOPMENT CORP. | Primary recipient | $2,114,418.52 |
FELDKAMP ENTERPRISES, INC. | Sub-recipient | $175,775.00 |
FOWLER ELECTRIC CO. | Sub-recipient | $153,224.00 |
Steelbuildings C Michigan | Sub-recipient | $148,382.00 |
Luketic Concrete Inc | Sub-recipient | $146,450.00 |
Outdoor Enterprise | Sub-recipient | $75,500.00 |
Synecky Construction Inc | Sub-recipient | $62,000.00 |
Summit Painting | Sub-recipient | $50,527.05 |
Combs Interior Specialties Incorporated | Sub-recipient | $41,300.00 |
DALMATIAN FIRE, INC. | Sub-recipient | $39,678.00 |
FENCE MASTERS | Sub-recipient | $37,244.42 |