Contract: WALSH CONSTRUCTION COMPANY
Primary Recipient
WALSH CONSTRUCTION COMPANY
Amount
$48,146,168.47
Award Date
9/09/2009
Administering Agency
U.S. Army Corps of Engineers / U.S. Army Corps of Engineers - civil program financing only
CDFA Number
CDFA Program Title
Description
Major Rehabilitation, Stage III, Canal Walls, Lockport Pool, Illinois Waterway, Lockport Lock: - This project consists of the installation of pre-cast panels on the water side of the existing perched canal wall to prevent seepage and to protect the histor
Recipients Connected to Award
Recipient | Role | Amount |
---|---|---|
WALSH CONSTRUCTION COMPANY | Primary recipient | $41,540,473.22 |
HAYWARD BAKER, INC. | Sub-recipient | $2,667,719.51 |
J&B STEEL ERECTORS, INC. | Sub-recipient | $1,260,702.10 |
STEPPO SUPPLY & CONSTRUCTION | Sub-recipient | $1,042,760.55 |
B NEXT CONSTRUCTION INC | Sub-recipient | $716,372.25 |
Luise, Inc. | Sub-recipient | $396,160.20 |
BIDCO MARINE GROUP INC. | Sub-recipient | $208,894.13 |
GFS FENCE, GUARDRAIL, & SIGNAGE, INC. | Sub-recipient | $82,768.18 |
Quanta Services, Inc. | Sub-recipient | $78,095.26 |
PAGE SECURITY | Sub-recipient | $72,703.14 |
COLLINS ENGINEERS, INCORPORATED | Sub-recipient | $44,531.17 |
INTERRA, INC | Sub-recipient | $16,610.83 |
INJECTION & WATERPROOFING SYSTEMS, INC. | Sub-recipient | $13,430.03 |
Western Remac, Inc. | Sub-recipient | $3,534.22 |
HOMER TREE SERVICE, INC. | Sub-recipient | $1,413.68 |