Columbia County, Ga., funds by U.S. Army Corps of Engineers
Listing $1,474,669.13 in stimulus funds from U.S. Army Corps of Engineers for Columbia
Note: For some programs where states do not report where money will be distributed across the state, we do not have the allocation for individual counties. Those programs include: Medicaid, unemployment benefits and food stamps. Those amounts are included in the totals for where the state agency receiving that money is located.
Amount refers to both the amount of stimulus funding going toward the project and the face value of the loan.
Recipient | Amount | Description | Federal Dept./Agency | Date |
---|---|---|---|---|
COUNTY OF COLUMBIA | $754,448 | Installation of potable water line to three(3) Corps of Engineers campgrounds. | U.S. Army Corps of Engineers - civil program financing only | 9/30/2009 |
MUNDY & SALLEY INCORPORATED | $624,661 |
ASBESOS CABLE TRAY REPLACEMENT
This spending item is part of a $2,035,219 allocation.
See details
|
U.S. Army Corps of Engineers - civil program financing only | 8/27/2009 |
ALL AMERICAN ELECTRICAL SERVICES, LLC | $48,180 |
Construct Battery Room, Hartwell Dam, Georgia: Provide all labor, material, equipment, incidentals and transportation to construct Battery Room at Hartwell Dam.
This spending item is part of a $350,132 allocation.
See details
|
U.S. Army Corps of Engineers - civil program financing only | 9/29/2009 |
ALL AMERICAN ELECTRICAL SERVICES, LLC | $47,380 |
Construct Comfort Stations, Twin Lakes Campground, Watsadler Campground and Springfield Campground, Lake Hartwell, GA: Design and construct Comfort Stations for 3 campgrounds. Each site will be demolished and re-built.
This spending item is part of a $900,514 allocation.
See details
|
U.S. Army Corps of Engineers - civil program financing only | 9/29/2009 |