Hart County, Ga., funds by U.S. Army Corps of Engineers
Listing $4,799,244.01 in stimulus funds from U.S. Army Corps of Engineers for Hart
Note: For some programs where states do not report where money will be distributed across the state, we do not have the allocation for individual counties. Those programs include: Medicaid, unemployment benefits and food stamps. Those amounts are included in the totals for where the state agency receiving that money is located.
Amount refers to both the amount of stimulus funding going toward the project and the face value of the loan.
Recipient | Amount | Description | Federal Dept./Agency | Date |
---|---|---|---|---|
EATON CORPORATION | $1,104,004 |
As a part of the Hartwell Lake project #007380 at Hartwell, GA, design and install station svc switchgear and perform turnkey replacement of the switchgear
This spending item is part of a $1,743,815 allocation.
See details
|
U.S. Army Corps of Engineers - civil program financing only | 9/28/2009 |
TC&S/F-W, L.L.C. | $1,033,000 | American Recovery and Reinvestment Act (ARRA) Funds in the amount of $1,033,000.00 are being obligated at this time for construction of 5-6 campsites at Hart Group Recreation Area to serve as a Volunteer Village, rehabilitation of aging/deteriorating camp | U.S. Army Corps of Engineers - civil program financing only | 12/02/2009 |
EATON CORPORATION | $624,889 |
As a part of the Hartwell Lake project #007380 at Hartwell, GA, design and install motor control; perform turnkey replacement of the motor control equipment
This spending item is part of a $1,061,090 allocation.
See details
|
U.S. Army Corps of Engineers - civil program financing only | 9/28/2009 |
WHITE HAWK TODD A JOINT VENTURE | $540,011 |
Paving at 4 sites at Lake Hartwell - Oconee Point Campground, Elrod Ferry Recreation Area, Coneross Campground & Friendship Boat Ramp: Provide paviing for all sites.
This spending item is part of a $1,196,908 allocation.
See details
|
U.S. Army Corps of Engineers - civil program financing only | 9/30/2009 |
FERGUSON-WILLIAMS LLC | $500,000 | , Maintenance, Repair, Minor Construction and Operation of Hartwell Lake, Dam, Power Plant, and Clemson Pumping Station, Hartwell, Georgia, is modified as shown in the following Summary of Changes. Funding Modification P00038 (RECOVERY | U.S. Army Corps of Engineers - civil program financing only | 6/02/2009 |
WHITE HAWK TODD A JOINT VENTURE | $316,255 |
Construct Comfort Stations, Twin Lakes Campground, Watsadler Campground and Springfield Campground, Lake Hartwell, GA: Design and construct Comfort Stations for 3 campgrounds. Each site will be demolished and re-built.
This spending item is part of a $900,514 allocation.
See details
|
U.S. Army Corps of Engineers - civil program financing only | 9/29/2009 |
MCNAUGHTON-MCKAY SOUTHEAST, INC. | $289,240 | Revcovery Project# 7380 - RP# Station Programmable Logic Controller Equipment for Hartwell PowerPlant, Hartwell, Georgia. The controls will be used to upgrade existing plant controls, including turbines. Current technology is outdated. The technology th | U.S. Army Corps of Engineers - civil program financing only | 7/07/2010 |
WHITE HAWK TODD A JOINT VENTURE | $222,251 |
Gantry Crane Corrosion Repair, Hartwell Dam: Furnish all labor, material, equipment, incidentals, supervision and transportation for work to provide repairs for the Gantry Crane Corrosion.
This spending item is part of a $583,221 allocation.
See details
|
U.S. Army Corps of Engineers - civil program financing only | 9/30/2009 |
WHITE HAWK TODD A JOINT VENTURE | $113,130 |
Construct Battery Room, Hartwell Dam, Georgia: Provide all labor, material, equipment, incidentals and transportation to construct Battery Room at Hartwell Dam.
This spending item is part of a $350,132 allocation.
See details
|
U.S. Army Corps of Engineers - civil program financing only | 9/29/2009 |
BLACK ELECTRICAL SUPPLY, INC | $56,464 | As a part of U.S. ARMY CORPS OF ENGINEERS, construction on Hartwell Project 111610 | U.S. Army Corps of Engineers - civil program financing only | 2/23/2010 |