Smith County, Tenn., funds by U.S. Army Corps of Engineers
Listing $7,368,114.04 in stimulus funds from U.S. Army Corps of Engineers for Smith
Note: For some programs where states do not report where money will be distributed across the state, we do not have the allocation for individual counties. Those programs include: Medicaid, unemployment benefits and food stamps. Those amounts are included in the totals for where the state agency receiving that money is located.
Amount refers to both the amount of stimulus funding going toward the project and the face value of the loan.
Recipient | Amount | Description | Federal Dept./Agency | Date |
---|---|---|---|---|
T.E.M. GROUP, INC. | $3,305,683 | Construcion Services to replace the control power cables at the Center Hill Power Plant, Lancaster, Tn U.S. Army Corps of Engineers | U.S. Army Corps of Engineers - civil program financing only | 3/31/2010 |
T.E.M. GROUP, INC. | $908,877 | Construcion Services to replace the control power cables at the Center Hill Power Plant, Lancaster, Tn U.S. Army Corps of Engineers | U.S. Army Corps of Engineers - civil program financing only | 9/30/2009 |
ROMTEC, INC. | $734,246 | THREE RESTROOM FACILITIES (BUILDING AND INSTALLATION) FOR THE CORDELL HULL PROJECTS | U.S. Army Corps of Engineers - civil program financing only | 9/25/2009 |
APPLIED INDUSTRIAL TECHNOLOGIES, INC. | $494,257 | Services to repair existing sluice hydraulic equipment at Center Hill, Dale Hollow, and Wolf Creek projects of the Nashville District U.S. Army Corps of Engineers. | U.S. Army Corps of Engineers - civil program financing only | 9/16/2009 |
JOHN BOUCHARD & SONS CO. | $397,272 | Supply and deliver generator air coolers for the Center Hill Power Plant, Units One and Three, Nashville District U.S. Army Corps of Engineers, in accordance with specifications and drawings. | U.S. Army Corps of Engineers - civil program financing only | 9/28/2009 |
ENVIRONMENTAL, SAFETY & HEALTH, INC. | $274,529 | Defeated Creek Campground Renovations, Carthage Tennessee | U.S. Army Corps of Engineers - civil program financing only | 9/28/2009 |
DIAMOND DRILLING & SUPPLY COMPANY | $268,595 |
Construction services for wire saw slot cutting
This spending item is part of a $413,934 allocation.
See details
|
U.S. Army Corps of Engineers - civil program financing only | 9/15/2009 |
MONTGOMERY ELECTRIC COMPANY | $211,829 | Services to install waterline at Defeated Creek Campground, Cordell Hull project, Carthage, TN of the Nashville District U.S. Army Corps of Engineers. | U.S. Army Corps of Engineers - civil program financing only | 9/29/2009 |
NORRIS DESIGN LLC | $184,773 | 'Supply new furniture for the Cordell Hull Resource Manager's Office, Carthage, TN, of the Nashville District U.S. Army Corps of Engineers.' | U.S. Army Corps of Engineers - civil program financing only | 9/10/2009 |
EATHERLY GROUP, INC | $134,722 |
Replace the Cordell Hull Natural Resource Manager's Office and Display Area Facility that was destroyed by fire in 2008.
This spending item is part of a $2,923,847 allocation.
See details
|
U.S. Army Corps of Engineers - civil program financing only | 8/28/2009 |
Rackley Roofing Co Inc | $101,110 |
Replace the Cordell Hull Natural Resource Manager's Office and Display Area Facility that was destroyed by fire in 2008.
This spending item is part of a $2,923,847 allocation.
See details
|
U.S. Army Corps of Engineers - civil program financing only | 8/28/2009 |
BETTER BUILT CONSTRUCTION SERVICES INC | $85,714 |
Construction services for wire saw slot cutting
This spending item is part of a $413,934 allocation.
See details
|
U.S. Army Corps of Engineers - civil program financing only | 9/15/2009 |
TENN-KY. AUTOMATIC SPRINKLER CO., INC. | $60,247 |
Replace the Cordell Hull Natural Resource Manager's Office and Display Area Facility that was destroyed by fire in 2008.
This spending item is part of a $2,923,847 allocation.
See details
|
U.S. Army Corps of Engineers - civil program financing only | 8/28/2009 |
A & K CONSTRUCTION, INC. | $59,625 |
Construction services for wire saw slot cutting
This spending item is part of a $413,934 allocation.
See details
|
U.S. Army Corps of Engineers - civil program financing only | 9/15/2009 |
WALTER A. WOOD SUPPLY CO., INC. | $53,930 | Various materials.....pipe, valves and fittings.....misc. | U.S. Army Corps of Engineers - civil program financing only | 9/25/2009 |
GIPSON PAVING CONSTRUCT PAVIN | $20,750 | Construction of concrete sidewalks for 2 restrooms and 1 showerhouse for Defeated Creek Campground, Cordell Hull Project, Carthage, Tn, of the Nashville District U.S. Army Corps of Engineers | U.S. Army Corps of Engineers - civil program financing only | 6/15/2010 |
WALTER A. WOOD SUPPLY CO., INC. | $19,153 | Misc materials...pipe valves and fittings | U.S. Army Corps of Engineers - civil program financing only | 9/18/2009 |
MONTGOMERY ELECTRIC COMPANY | $13,425 | Project to repair dip in roadway at entrance to Dedeated Creek Recreation Area, Cordell Hull Lake, Smith County, TN | U.S. Army Corps of Engineers - civil program financing only | 9/29/2009 |
MONTGOMERY ELECTRIC COMPANY | $9,704 | Services to replace waterline and hydrant near the Cordell Hull Resource Managers Office, Carthage, TN, of the Nashville District U.S. Army Corps of Engineers. | U.S. Army Corps of Engineers - civil program financing only | 9/29/2009 |
MONTGOMERY ELECTRIC COMPANY | $8,990 | Project is to install 2 water line, gate valves, 4 tight line for sewer, excavate for installation of 50KVA transformer, install 3 conduit & pull boxes for electrical installation to prepare site for new shower house at Defeated Creek Campground, Cordell | U.S. Army Corps of Engineers - civil program financing only | 9/29/2009 |
MONTGOMERY ELECTRIC COMPANY | $7,997 | Project to install 2 water& sewer lines, excavated for installation of 25KVA transformer, place 3 conduit for electrical installation, set 400A main panel to prepare site for new restroom right recreation bank Cordell Hull Lake, Smith County TN | U.S. Army Corps of Engineers - civil program financing only | 9/29/2009 |
MONTGOMERY ELECTRIC COMPANY | $7,421 | Furnish labor & supervision to install 2 water & sewer lines,excavate for installation of new transformer.Place 3 conduit & pull box for electrical installation to prepare site for new restroom at Tailwater area, Cordell Hull lake, Smith County, TN | U.S. Army Corps of Engineers - civil program financing only | 9/29/2009 |
WALTER A. WOOD SUPPLY CO., INC. | $5,265 | various materials----pipe valves fittings | U.S. Army Corps of Engineers - civil program financing only | 9/21/2009 |
ANDERSON PIPING, INC. | $0 | Replacement of generator cooling water piping system at the Center Hill Power Plant, Lancaster, TN, of the Nashville District U.S. Army Corps of Engineers | U.S. Army Corps of Engineers - civil program financing only | 4/07/2011 |