Recovery Tracker

How Much Stimulus Funding is Going to Your County?

Harris County, Texas, funds by U.S. Army Corps of Engineers

Listing $100,959,076.11 in stimulus funds from U.S. Army Corps of Engineers for Harris

Note: For some programs where states do not report where money will be distributed across the state, we do not have the allocation for individual counties. Those programs include: Medicaid, unemployment benefits and food stamps. Those amounts are included in the totals for where the state agency receiving that money is located.

Amount refers to both the amount of stimulus funding going toward the project and the face value of the loan.

Recipient Amount Description Federal Dept./Agency Date
KING FISHER MARINE SERVICE, L.P. $34,246,002 As part of maintenance on Houston-Galveston Navigation Channels project, the contract provides for design and construction for the rehabilitation and increased capacity of multiple existing sites along the Houston Ship Channel. These sites are used to co
This spending item is part of a $52,942,206 allocation. See details
U.S. Army Corps of Engineers - civil program financing only 8/13/2009
LUHR BROS., INC. $11,555,234 $33,021,247.68 (TOTAL CONTRACT) & $11,186,043.00 (ARRA FUNDS). AS PART OF THE USACE ARRA PROGRAM THIS IS THE DESIGN BUILD OF THE BOLIVAR 288 ACRE MARSH FOR THE HOUSTON-GALVESTON NAVIGATION CHANNEL PHASE II, IN HARRIS AND GALVESTON COUNTIES, TEXAS. U.S. Army Corps of Engineers - civil program financing only 5/25/2010
LECON, INC. $9,756,000 AS A PART OF THE USACE ARRA PROGRAM, THIS CONTRACT WAS AWARDED FOR RECOVERY, CHANNEL RECTIFICATION, CROQUET TO SOUTH POST OAK AND SEDIMENT REMOVAL, ROBIN BOULEVARD TO SH-288 IN HARRIS COUNTY, TEXAS U.S. Army Corps of Engineers - civil program financing only 4/23/2010
WESTON SOLUTIONS, INC. $9,340,909 As part of maintenance on Houston-Galveston Navigation Channels project, the contract provides for design and construction for the rehabilitation and increased capacity of multiple existing sites along the Houston Ship Channel. These sites are used to co
This spending item is part of a $52,942,206 allocation. See details
U.S. Army Corps of Engineers - civil program financing only 8/13/2009
RLB CONTRACTING, INC. $8,800,000 $33,021,247.68 (TOTAL CONTRACT) & $11,186,043.00 (ARRA FUNDS). AS PART OF THE USACE ARRA PROGRAM THIS IS THE DESIGN BUILD OF THE BOLIVAR 288 ACRE MARSH FOR THE HOUSTON-GALVESTON NAVIGATION CHANNEL PHASE II, IN HARRIS AND GALVESTON COUNTIES, TEXAS.
This spending item is part of a $11,186,043 allocation. See details
U.S. Army Corps of Engineers - civil program financing only 5/25/2010
LECON, INC. $6,515,658 RECOVERY - SIMS BAYOU, HOUSTON, TEXAS, STATE HWY 288 TO MYKAWA ROAD IN HARRIS COUNTY, TX, SEDIMENT REMOVAL AND CHANNEL REPAIRS U.S. Army Corps of Engineers - civil program financing only 9/24/2009
LUHR BROS., INC. $5,439,400 As part of maintenance on Houston-Galveston Navigation Channels project, the contract provides for design and construction for the rehabilitation and increased capacity of multiple existing sites along the Houston Ship Channel. These sites are used to co
This spending item is part of a $52,942,206 allocation. See details
U.S. Army Corps of Engineers - civil program financing only 8/13/2009
EROSION PREVENTION PRODUCTS, LLC $3,300,000 Central and South Florida Site 1 Impoundment Project. Strengthen existing L40 Levee with borrow material and armor the top and banks with soil cement and turf reinforcement mat. Other activities include clearing and grubbing, borrow excavation site and
This spending item is part of a $44,125,000 allocation. See details
U.S. Army Corps of Engineers - civil program financing only 8/24/2010
HDR ENGINEERING, INC. $2,367,349 $33,021,247.68 (TOTAL CONTRACT) & $11,186,043.00 (ARRA FUNDS). AS PART OF THE USACE ARRA PROGRAM THIS IS THE DESIGN BUILD OF THE BOLIVAR 288 ACRE MARSH FOR THE HOUSTON-GALVESTON NAVIGATION CHANNEL PHASE II, IN HARRIS AND GALVESTON COUNTIES, TEXAS.
This spending item is part of a $11,186,043 allocation. See details
U.S. Army Corps of Engineers - civil program financing only 5/25/2010
WAUKESHA-PEARCE INDUSTRIES, INC. $1,255,277 As part of maintenance on Houston-Galveston Navigation Channels project, the contract provides for design and construction for the rehabilitation and increased capacity of multiple existing sites along the Houston Ship Channel. These sites are used to co
This spending item is part of a $52,942,206 allocation. See details
U.S. Army Corps of Engineers - civil program financing only 8/13/2009
GLOBALOGIX, INC. $1,197,594 The scope of the project is to upgrade existing supervisor control and data acquisition systems, improve efficiency in the aging lock and dams in a 223 mile stretch of the Tenn-Tombigbee waterway from Demopolis, Ala, to the Tennesse River. The water moni U.S. Army Corps of Engineers - civil program financing only 5/05/2010
McCollom Interests L L C $1,131,000 As part of maintenance on Houston-Galveston Navigation Channels project, the contract provides for design and construction for the rehabilitation and increased capacity of multiple existing sites along the Houston Ship Channel. These sites are used to co
This spending item is part of a $52,942,206 allocation. See details
U.S. Army Corps of Engineers - civil program financing only 8/13/2009
LANDTECH CONSULTANTS INC $838,034 PERIMETER BOUNDARY RETRACEMENT SURVEY, BELTON LAKE AND WHITNEY LAKE, TEXAS U.S. Army Corps of Engineers - civil program financing only 9/28/2009
AECOM TECHNICAL SERVICES, INC. $692,638 A&E services to assist the Galveston District to prepare a Request for Proposal (RFP) for the Government for design and reconstruction of placement areas used for the Houston-Galveston Navigation Channel (HGNC). The features to be defined in the RFP inc U.S. Army Corps of Engineers - civil program financing only 6/04/2009
PHILADELPHIA GEAR CORPORATION $462,472 Manufacture of four gearboxes. U.S. Army Corps of Engineers - civil program financing only 8/17/2009
SUN COAST RESOURCES, INC. $403,500 As part of maintenance on Houston-Galveston Navigation Channels project, the contract provides for design and construction for the rehabilitation and increased capacity of multiple existing sites along the Houston Ship Channel. These sites are used to co
This spending item is part of a $52,942,206 allocation. See details
U.S. Army Corps of Engineers - civil program financing only 8/13/2009
Griffin Dewatering Corporation $351,261 Construction Channel Improvement Project, Mission Reach, Phase 2a, San Antonio, Texas.
This spending item is part of a $23,534,095 allocation. See details
U.S. Army Corps of Engineers - civil program financing only 12/21/2009
TOLUNAY-WONG ENGINEERS, INC. $334,040 $33,021,247.68 (TOTAL CONTRACT) & $11,186,043.00 (ARRA FUNDS). AS PART OF THE USACE ARRA PROGRAM THIS IS THE DESIGN BUILD OF THE BOLIVAR 288 ACRE MARSH FOR THE HOUSTON-GALVESTON NAVIGATION CHANNEL PHASE II, IN HARRIS AND GALVESTON COUNTIES, TEXAS.
This spending item is part of a $11,186,043 allocation. See details
U.S. Army Corps of Engineers - civil program financing only 5/25/2010
MB Western Construction Services, L.P. $329,454 As part of maintenance on Houston-Galveston Navigation Channels project, the contract provides for design and construction for the rehabilitation and increased capacity of multiple existing sites along the Houston Ship Channel. These sites are used to co
This spending item is part of a $52,942,206 allocation. See details
U.S. Army Corps of Engineers - civil program financing only 8/13/2009
HERTZ EQUIPMENT RENTAL CORPORATION $312,493 American Recovery & Reinvestment Act (ARRA) funding was obligated on USACE Kansas City District Contract No. DACW41-99-D-9001 for 'Maywood Chemical Superfund Site-Specific Environmental Remediation' as bilateral Modification No. 0004 under Task Order No.
This spending item is part of a $49,138,392 allocation. See details
U.S. Army Corps of Engineers - civil program financing only 6/22/2009
CALLAN MARINE LTD $248,675 $33,021,247.68 (TOTAL CONTRACT) & $11,186,043.00 (ARRA FUNDS). AS PART OF THE USACE ARRA PROGRAM THIS IS THE DESIGN BUILD OF THE BOLIVAR 288 ACRE MARSH FOR THE HOUSTON-GALVESTON NAVIGATION CHANNEL PHASE II, IN HARRIS AND GALVESTON COUNTIES, TEXAS.
This spending item is part of a $11,186,043 allocation. See details
U.S. Army Corps of Engineers - civil program financing only 5/25/2010
HERTZ EQUIPMENT RENTAL CORPORATION $235,729 American Recovery & Reinvestment Act (ARRA) funding was obligated on USACE Kansas City District Contract No. DACW41-99-D-9001 for 'Maywood Chemical Superfund Site-Specific Environmental Remediation' as bilateral Modification No. 0004 under Task Order No.
This spending item is part of a $49,138,392 allocation. See details
U.S. Army Corps of Engineers - civil program financing only 6/22/2009
NELSON EQUIPMENT, LTD. $180,726 As part of maintenance on Houston-Galveston Navigation Channels project, the contract provides for design and construction for the rehabilitation and increased capacity of multiple existing sites along the Houston Ship Channel. These sites are used to co
This spending item is part of a $52,942,206 allocation. See details
U.S. Army Corps of Engineers - civil program financing only 8/13/2009
LANDTECH CONSULTANTS INC $179,981 PERIMETER BOUNDARY RETRACEMENT SURVEY, STILLHOUSE HOLLOW LAKE,TX U.S. Army Corps of Engineers - civil program financing only 12/29/2009
MUSTANG MACHINERY COMPANY, LTD. $157,753 As part of maintenance on Houston-Galveston Navigation Channels project, the contract provides for design and construction for the rehabilitation and increased capacity of multiple existing sites along the Houston Ship Channel. These sites are used to co
This spending item is part of a $52,942,206 allocation. See details
U.S. Army Corps of Engineers - civil program financing only 8/13/2009
HERTZ EQUIPMENT RENTAL CORPORATION $136,621 American Recovery & Reinvestment Act (ARRA) funding was obligated on USACE Kansas City District Contract No. DACW41-99-D-9001 for 'Maywood Chemical Superfund Site-Specific Environmental Remediation' as bilateral Modification No. 0004 under Task Order No.
This spending item is part of a $49,138,392 allocation. See details
U.S. Army Corps of Engineers - civil program financing only 6/22/2009
FOUR SEASONS EQUIPMENT, INC. $134,392 As part of maintenance on Houston-Galveston Navigation Channels project, the contract provides for design and construction for the rehabilitation and increased capacity of multiple existing sites along the Houston Ship Channel. These sites are used to co
This spending item is part of a $52,942,206 allocation. See details
U.S. Army Corps of Engineers - civil program financing only 8/13/2009
HYDROGRAPHIC CONSULTANTS, LTD $132,382 $33,021,247.68 (TOTAL CONTRACT) & $11,186,043.00 (ARRA FUNDS). AS PART OF THE USACE ARRA PROGRAM THIS IS THE DESIGN BUILD OF THE BOLIVAR 288 ACRE MARSH FOR THE HOUSTON-GALVESTON NAVIGATION CHANNEL PHASE II, IN HARRIS AND GALVESTON COUNTIES, TEXAS.
This spending item is part of a $11,186,043 allocation. See details
U.S. Army Corps of Engineers - civil program financing only 5/25/2010
STELL ENVIRONMENTAL ENTERPRISES, INC. $129,630 As a part of Bellfort Landfill Phase II project, the City of Houston has requested assistance throughthe EPA Targeted Brownsfield Assessment (TBA) Program for a limited environemntal investigation at the 3300 Bellfort St. landfill site. The site is bound U.S. Army Corps of Engineers - civil program financing only 3/08/2010
Sandoval Engineers & Surveyors Inc $97,812 As part of maintenance on Houston-Galveston Navigation Channels project, the contract provides for design and construction for the rehabilitation and increased capacity of multiple existing sites along the Houston Ship Channel. These sites are used to co
This spending item is part of a $52,942,206 allocation. See details
U.S. Army Corps of Engineers - civil program financing only 8/13/2009
UNITED RENTALS, INC. $94,109 As part of maintenance on Houston-Galveston Navigation Channels project, the contract provides for design and construction for the rehabilitation and increased capacity of multiple existing sites along the Houston Ship Channel. These sites are used to co
This spending item is part of a $52,942,206 allocation. See details
U.S. Army Corps of Engineers - civil program financing only 8/13/2009
LANDTECH CONSULTANTS INC $83,382 PLANIMETRIC, AND UTILITY SURVEYS YEGUA CREEK PARK AT SOMERVILLE LAKE, WASHINGTON COUNTY, TEXASTHE CONTRACTOR SHALL PERFORM FIELD TOPOGRAPHIC, PLANIMETRIC, AND UTILITY SURVEYS, OFFICE COMPUTATIONS, AND 3D DIGITAL MAPPING FOR USE IN DEVELOPING PLANS AND SPE U.S. Army Corps of Engineers - civil program financing only 9/18/2010
URS GROUP, INC. $72,403 As a part of Regulatory Program, Recovery Act, Project Number 107300 is for the analysis of historical and existing aquatic resources on the Bad River in northern Wisconsin. U.S. Army Corps of Engineers - civil program financing only 4/23/2010
CROUCH ENVIRONMENTAL SERVICES INC $66,985 The work to be performed is preparation of an environmental assessment (EA) for the proposed expansion of placement areas (PA) 14 and 15 along the Houston Ship Channel. This includes conducting technical, research, and field work necessary to prepare the
This spending item is part of a $102,322 allocation. See details
U.S. Army Corps of Engineers - civil program financing only 9/20/2009
COASTAL SURVEYING OF TEXAS, INC. $60,900 $33,021,247.68 (TOTAL CONTRACT) & $11,186,043.00 (ARRA FUNDS). AS PART OF THE USACE ARRA PROGRAM THIS IS THE DESIGN BUILD OF THE BOLIVAR 288 ACRE MARSH FOR THE HOUSTON-GALVESTON NAVIGATION CHANNEL PHASE II, IN HARRIS AND GALVESTON COUNTIES, TEXAS.
This spending item is part of a $11,186,043 allocation. See details
U.S. Army Corps of Engineers - civil program financing only 5/25/2010
Accutech Consultants, LLC $54,048 Provide construction phase services (submittals, onsite engineering tech, and construction meeting) for Phase 2a for the Construction of the Channel Improvement, Mission Reach, San Antonio, Texas. SAN ANTONIO MISSION REACH SAN ANTONIO MISSION REACH
This spending item is part of a $889,436 allocation. See details
U.S. Army Corps of Engineers - civil program financing only 3/24/2010
BWI COMPANIES, INC. $42,372 As part of maintenance on Houston-Galveston Navigation Channels project, the contract provides for design and construction for the rehabilitation and increased capacity of multiple existing sites along the Houston Ship Channel. These sites are used to co
This spending item is part of a $52,942,206 allocation. See details
U.S. Army Corps of Engineers - civil program financing only 8/13/2009
HERTZ EQUIPMENT RENTAL CORPORATION $35,728 American Recovery & Reinvestment Act (ARRA) funding was obligated on USACE Kansas City District Contract No. DACW41-99-D-9001 for 'Maywood Chemical Superfund Site-Specific Environmental Remediation' as bilateral Modification No. 0004 under Task Order No.
This spending item is part of a $49,138,392 allocation. See details
U.S. Army Corps of Engineers - civil program financing only 6/22/2009
AEROTEK, INC. $32,160 $33,021,247.68 (TOTAL CONTRACT) & $11,186,043.00 (ARRA FUNDS). AS PART OF THE USACE ARRA PROGRAM THIS IS THE DESIGN BUILD OF THE BOLIVAR 288 ACRE MARSH FOR THE HOUSTON-GALVESTON NAVIGATION CHANNEL PHASE II, IN HARRIS AND GALVESTON COUNTIES, TEXAS.
This spending item is part of a $11,186,043 allocation. See details
U.S. Army Corps of Engineers - civil program financing only 5/25/2010
CORT BUSINESS SERVICES CORPORATION $31,732 As part of maintenance on Houston-Galveston Navigation Channels project, the contract provides for design and construction for the rehabilitation and increased capacity of multiple existing sites along the Houston Ship Channel. These sites are used to co
This spending item is part of a $52,942,206 allocation. See details
U.S. Army Corps of Engineers - civil program financing only 8/13/2009
WILLIAMS SCOTSMAN, INC. $29,559 As part of maintenance on Houston-Galveston Navigation Channels project, the contract provides for design and construction for the rehabilitation and increased capacity of multiple existing sites along the Houston Ship Channel. These sites are used to co
This spending item is part of a $52,942,206 allocation. See details
U.S. Army Corps of Engineers - civil program financing only 8/13/2009
RSC EQUIPMENT RENTAL, INC. $28,208 As part of maintenance on Houston-Galveston Navigation Channels project, the contract provides for design and construction for the rehabilitation and increased capacity of multiple existing sites along the Houston Ship Channel. These sites are used to co
This spending item is part of a $52,942,206 allocation. See details
U.S. Army Corps of Engineers - civil program financing only 8/13/2009
LANDTECH CONSULTANTS INC $23,517 Survey - Los Ebanos Port of Entry U.S. Army Corps of Engineers - civil program financing only 8/24/2009
AMERICAN BUREAU OF SHIPPING $17,640 Stop Lock Barge - ABS Review U.S. Army Corps of Engineers - civil program financing only 12/14/2009
G & H DIVERSIFIED MFG., L.P. $12,401 G&H BID ON THIS JOB TO ESTABLISH HISTORY AS A SUPPLIER TO THE US GOVERNMENT. WE EXPECT THE PARTS TO PASS WITH FLYING COLORS AND TO HELP US GAIN FUTURE ORDERS FORM THE US GOVERNMENT. WE DELIVERY 24 PARTS. U.S. Army Corps of Engineers - civil program financing only 8/04/2009
Chris Ransome & Associates, Inc. $11,916 ARRA funded work for marine archeological surveys for the Houston Ship Channel, Chambers County, Texas
This spending item is part of a $111,744 allocation. See details
U.S. Army Corps of Engineers - civil program financing only 10/30/2009
ENVIRONMENTAL CHEMICAL CORPORATION $0 $33,021,247.68 (TOTAL CONTRACT) & $11,186,043.00 (ARRA FUNDS). AS PART OF THE USACE ARRA PROGRAM THIS IS THE DESIGN BUILD OF THE BOLIVAR 288 ACRE MARSH FOR THE HOUSTON-GALVESTON NAVIGATION CHANNEL PHASE II, IN HARRIS AND GALVESTON COUNTIES, TEXAS.
This spending item is part of a $11,186,043 allocation. See details
U.S. Army Corps of Engineers - civil program financing only 5/25/2010