Presidio County, Texas, funds by State, Department of
Listing $6,464,827.50 in stimulus funds from State, Department of for Presidio
Note: For some programs where states do not report where money will be distributed across the state, we do not have the allocation for individual counties. Those programs include: Medicaid, unemployment benefits and food stamps. Those amounts are included in the totals for where the state agency receiving that money is located.
Amount refers to both the amount of stimulus funding going toward the project and the face value of the loan.
Recipient | Amount | Description | Federal Dept./Agency | Date |
---|---|---|---|---|
MAGNUS PACIFIC CORPORATION | $5,959,555 |
Levee Rehabilitation, Surfacing, Placement of Rip Rap, Install SB Slurry Wall (660,000 SF), Temp & Perm Toe Drain, Vegitation & Erosion Control
This spending item is part of a $6,324,095 allocation.
See details
|
U.S. and Mexico International Boundary and Water Commission | 8/13/2010 |
TETRA TECH, INC. | $248,733 | As part of TAS 19-1079 (CONSTRUCTION MANAGEMENT SERVICES DURING THE CONSTRUCTION OF THE URBAN LEVEE REMEDIATION AT RIO GRANDE AND CIBOLO CREEK, PRESIDIO, TX)-The Urban Levee Improvements at Rio Grande and Cibolo Creek consist of an approximate 8.4 miles o | U.S. and Mexico International Boundary and Water Commission | 8/31/2010 |
LAND-MARK PROFESSIONAL SURVEYING INCORPORATED | $104,874 |
Levee Rehabilitation, Surfacing, Placement of Rip Rap, Install SB Slurry Wall (660,000 SF), Temp & Perm Toe Drain, Vegitation & Erosion Control
This spending item is part of a $6,324,095 allocation.
See details
|
U.S. and Mexico International Boundary and Water Commission | 8/13/2010 |
FUGRO CONSULTANTS, INC. | $82,845 |
Levee Rehabilitation, Surfacing, Placement of Rip Rap, Install SB Slurry Wall (660,000 SF), Temp & Perm Toe Drain, Vegitation & Erosion Control
This spending item is part of a $6,324,095 allocation.
See details
|
U.S. and Mexico International Boundary and Water Commission | 8/13/2010 |
814 SOLUTIONS, LLC | $68,820 |
Levee Rehabilitation, Surfacing, Placement of Rip Rap, Install SB Slurry Wall (660,000 SF), Temp & Perm Toe Drain, Vegitation & Erosion Control
This spending item is part of a $6,324,095 allocation.
See details
|
U.S. and Mexico International Boundary and Water Commission | 8/13/2010 |