Recovery Tracker

How Much Stimulus Funding is Going to Your County?

Cabell County, W.Va., funds by U.S. Army Corps of Engineers

Listing $1,935,313.18 in stimulus funds from U.S. Army Corps of Engineers for Cabell

Note: For some programs where states do not report where money will be distributed across the state, we do not have the allocation for individual counties. Those programs include: Medicaid, unemployment benefits and food stamps. Those amounts are included in the totals for where the state agency receiving that money is located.

Amount refers to both the amount of stimulus funding going toward the project and the face value of the loan.

Recipient Amount Description Federal Dept./Agency Date
TETRA TECH, INC. $601,547 As part of TAS 96-3135-PERIODIC INSPECTIONS, BIG SANDY BASIN-The purpose of Pis is to verify proper operation and maintenance, evaluate operational adequacy and structural stability, review design criteria to identify changes in current design standards, U.S. Army Corps of Engineers - civil program financing only 7/29/2009
TETRA TECH, INC. $372,696 As part of TAS 96-3135-LEVEE CERTIFICATION, MASSILLON LEVEE, OHIO-Contractor must review as-built information and collect supplemental data to meet the certification requirements outlines in 44 CFR 65.10 and detailed in National Flood Insurance Program fo
This spending item is part of a $499,997 allocation. See details
U.S. Army Corps of Engineers - civil program financing only 7/29/2009
STANTEC/INCA JV $294,880 Contractor shall provide all supplies, material, labor and supervision necessry for periodic inspection, Ohio river basin river miles 182.3 to 317.6.
This spending item is part of a $872,162 allocation. See details
U.S. Army Corps of Engineers - civil program financing only 7/30/2009
TETRA TECH, INC. $174,266 Comprehesive Stream Assessment Project. Background: The Army Corps of Engineers (USACE) Huntington District is developing a stream assessment methodology for perennial streams in West Virginia and Eastern Kentucky. Assessments will be based upon Hydrogeo U.S. Army Corps of Engineers - civil program financing only 3/29/2010
TRI-STATE COATING AND MACHINE CO., INC. $170,919 Pump shaft sleeves for the Huxtable Pumping Plant U.S. Army Corps of Engineers - civil program financing only 6/25/2009
URS GROUP, INC. $135,502 TAS::96 3136::TAS - SUPPORT ENGINEER RESEARCH AND DEVELOPMENT CENTER STREAM ASSESSMENT FOR HIGH GRADIENT STREAMS IN WV. U.S. Army Corps of Engineers - civil program financing only 9/04/2009
URS GROUP, INC. $88,554 TAS::96 3135::TAS - COORDINATION AND FACILITATION OF INITIAL PROJECT SCOPING MEETINGS U.S. Army Corps of Engineers - civil program financing only 7/08/2009
ROBINSON CONTRACTING, INC. $44,586 Jenkins House Electrical Upgrade U.S. Army Corps of Engineers - civil program financing only 9/28/2010
INTERNATIONAL PROMOTIONAL IDEAS INC $15,100 Safety Items U.S. Army Corps of Engineers - civil program financing only 7/23/2009
C. I. THORNBURG CO., INC. (THE) $14,750 PROVIDE SEWAGE LIFT STATION UPGRADE FOR ENVIRONMENTAL SAFETY AT BURNSVILLE LAKE, BURNSVILLE, WV U.S. Army Corps of Engineers - civil program financing only 3/17/2010
COSMOS TECHNOLOGIES INC. $13,028 Geotechnical services necessary to rehabilitate foundations drains to reduce risk of dam failure, sutton Lake, Sutton, WV U.S. Army Corps of Engineers - civil program financing only 6/28/2010
LEWIS ENVIRONMENTAL CONSULTING $6,721 The services to be provided under this contract will be accomplished by diving surveys at various locations for the purpose of identifying freshwater mussel communities in and near an area proposed for navigation channel maintenance dredging disposal acti
This spending item is part of a $23,805 allocation. See details
U.S. Army Corps of Engineers - civil program financing only 6/11/2009
B E ELECTRICAL SERVICES $2,764 AS A PART OF MAINTENENCE OF MOHAWK DAM FOR INSTALLATION OF CLASS IV ELECTRICAL POLE U.S. Army Corps of Engineers - civil program financing only 7/10/2009