Browse All Approved Stimulus Highway Projects
Road and bridge projects are expected to make up one of the biggest chunks of the jobs created in the stimulus package. Below, you’ll find a chart of more than 5,800 projects that have been approved by the U.S. Department of Transportation. Once given the green light, states can put the projects out to bid, contract them and begin construction work. So far, about 2,300 projects are under way.
Help us find out how much progress has been made on these projects by participating in our Stimulus Spot Check.
For more on the stimulus, check out our blog and resource page.
| State | County | Project Number | Project Description | Improvement Type | ARRA Funds Obligated |
|---|---|---|---|---|---|
| MONTANA | LEWIS AND CLARK | 5822002 | 0.83 mile overlay in Helena | Pavement Improvement | $383,990 |
| MONTANA | PARK | 7406007 | 0.7 mile mill and fill in Livingston | Pavement Improvement | $215,594 |
| MONTANA | MISSOULA | 8105014 | 0.8 mile mill and fill in Missoula | Pavement Improvement | $150,745 |
| MONTANA | MISSOULA | 8107019 | 0.17 mile mill and fill in Missoula | Pavement Improvement | $76,845 |
| MONTANA | MISSOULA | 8109002 | On the Scott Street overpass in Missoula, Bridge deck repair and replacing the surface with a high strength epoxy concrete. | Bridge Improvement | $2,013,827 |
| MONTANA | MISSOULA | 8113006 | 0.3 mile mill and fill in Missoula | Pavement Improvement | $119,570 |
| MONTANA | MISSOULA | 8117006 | Intersection & Signal Improvement in Missoula | Pavement Improvement | $689,800 |
| MONTANA | FALLON | 9013015 | Bridge Replacement Project | Pavement Improvement | $776,600 |
| MONTANA | MISSOULA | 8120005 | 2 mile mill and fill in Missoula | Pavement Improvement | $616,301 |
| MONTANA | MISSOULA | 8123001 | MULLAN RD BIKE/PED PATH-MSLACO (PENG) South side of State Urban Route 8123/Mullan Rd-Hard surfaced bike/ped path... | Other | $72,000 |
| MONTANA | MISSOULA | 8199088 | SIDEWALK RAMPS-MISSOULA (PENG) Along various routes within the Missoula urban limits-ADA sidewalk ramps.. | Other | $20,000 |
| MONTANA | MISSOULA | 8199089 | GREENOUGH DRIVE SIDEWALKS-MSLA (PENG) Both sides of Greenough Drive between Madison Ave & Water Works Hill Trailhead-Sidewalks... | Other | $30,000 |
| MONTANA | BLAINE | 9003032 | Bridge & Approach Replacement without added Capacity | Bridge Replacement | $2,402,036 |
| MONTANA | MISSOULA | 8119001 | NORTH HIGGINS BIKE/PED-MSLA (PENG) Along both sides of State Urban Route 8119/Higgins Ave-Sidewalks, bike lanes, lighting.. | Other | $125,000 |
| N MARIANA | STATEWIDE | 31014 | CROSS ISLAND RD, PHASE II RECON, WIDENING, DRAINAGE IMPRVMTS, 500 FT PAST INTERSXN W/KAGMAN RD TO INTERSXN W/TALOFOFO RD (1.73 MI) | Other | $4,500,000 |
| NEBRASKA | DEUEL | 802090 | Resurf. | Pavement Improvement | $6,943,834 |
| NEBRASKA | JEFFERSON | 151113 | Br. | Bridge Replacement | $2,966,171 |
| NEBRASKA | PHELPS | 233105 | Resurf., S. Shld. | Pavement Improvement | $2,601,872 |
| NEBRASKA | BUFFALO | 304148 | Urban | Pavement Improvement | $1,645,634 |
| NEBRASKA | HALL | 344131 | Resurf. | Pavement Improvement | $5,132,648 |
| NEBRASKA | LANCASTER | 346139 | Resurf., S. Shld. | Pavement Improvement | $2,296,813 |
| NEBRASKA | DAKOTA | 354118 | Gr., Culv., Br. | Bridge Replacement | $1,944,384 |
| NEBRASKA | OTOE | 502128 | Resurf., S. Shld., Str. | Pavement Improvement | $4,907,360 |
| NEBRASKA | VALLEY | 704107 | Gr., Surf., Br. | Bridge Improvement | $1,717,017 |
| NEBRASKA | KIMBALL | 712109 | Resurf. | Pavement Improvement | $4,633,135 |
| NEBRASKA | ADAMS | 64125 | Resurf., S. Shld., Br. Repair | Pavement Improvement | $3,665,228 |
| NEBRASKA | CHEYENNE | 802093 | Joint Seal, Diamond Grinding | Pavement Improvement | $1,380,504 |
| NEBRASKA | LINCOLN | 804104 | Br. Deck Overlay | Bridge Improvement | $1,315,548 |
| NEBRASKA | DAWSON | 804129 | Br. Deck Overlay | Bridge Improvement | $1,050,940 |
| NEBRASKA | LINCOLN | 804133 | Joint Repair, Diamond Grinding | Pavement Improvement | $2,164,435 |
| NEBRASKA | DAWSON | 805069 | Resurf., S. Shld. | Pavement Improvement | $6,670,500 |
| NEBRASKA | HALL | 806097 | Resurf. | Pavement Improvement | $5,255,421 |
| NEBRASKA | DOUGLAS | 809889 | Gr., Surf., S. Shld. | Pavement Widening | $16,486,652 |
| NEBRASKA | THOMAS | 833106 | Viaduct | Bridge Replacement | $6,943,648 |
| NEBRASKA | CHERRY | 834113 | Resurf., S. Shld. | Pavement Improvement | $3,914,863 |
| NEBRASKA | LOUP | 913107 | Resurf., S. Shld. | Pavement Improvement | $2,135,795 |
| NEBRASKA | PLATTE | 915121 | Resurf. | Pavement Improvement | $3,745,305 |
| NEBRASKA | COLFAX | 916111 | Resurf. | Pavement Improvement | $2,395,806 |
| NEBRASKA | DIXON | 1164102 | Br. | Bridge Replacement | $372,654 |
| NEBRASKA | THAYER | 1365111 | Resurf. | Pavement Improvement | $1,635,326 |
| NEBRASKA | GAGE | 1366116 | Resurf., S. Shld. | Pavement Improvement | $3,304,415 |
| NEBRASKA | JEFFERSON | 1366118 | Resurf. | Pavement Improvement | $2,878,863 |
| NEBRASKA | NEMAHA | 1367122 | Br. Repair/Rehab. | Bridge Improvement | $5,403,400 |
| NEBRASKA | BOX BUTTE | 3854129 | Resurf., S. Shld. | Pavement Improvement | $3,139,546 |
| NEBRASKA | DOUGLAS | 4809776 | Br. | Bridge Replacement | $2,018,451 |
| NEBRASKA | DOUGLAS | 4809777 | Br. | Bridge Improvement | $1,665,817 |
| NEBRASKA | DOUGLAS | 4809778 | Gr., Culv., Surf., Br. Removal | Pavement Improvement | $13,955,039 |
| NEBRASKA | DOUGLAS | 4809787 | Br. | Bridge Improvement | $3,296,000 |
| NEBRASKA | REDWILLOW | 6156002 | Urban | Pavement Improvement | $1,157,694 |
| NEBRASKA | CLAY | S18B104 | Gr., Culv., Resurf. | Pavement Improvement | $1,947,585 |