Alabama • AL-04 Congressional District
Top 10 Largest Contracts
I-59 CONCRETE PAVE REHAB WITH UNBONDED OVE... | AL / Etowah |
$48,092,008
|
PLANE/RESURFACE SR-17 FROM 0.7 MILE NORTH ... | AL / Lamar |
$6,084,240
|
WIDENING & RESURFACING SR-1 (US-431) FROM ... | AL / Marshall |
$3,761,469
|
RESURFACING AND STRIPING SR-17 FROM LAMAR ... | AL / Marion |
$1,785,816
|
RESURFACE, STRIPING SR-75 FROM CR-363 (BRO... | AL / Blount |
$1,783,600
|
RESURFACE SR-129 FROM SR-171 (US-43) TO CR... | AL / Fayette |
$1,635,520
|
RESURFACING SR-69 FROM I-65 IN GOOD HOPE T... | AL / Franklin |
$1,614,641
|
RESURFACE SR-118 FROM 4TH STREET IN CARBON... | AL / Walker |
$1,478,967
|
RESURFACE SR-33 FROM SR-74 TO NORTH END OF... | AL / Winston |
$1,006,784
|
RESURFACING AND STRIPING SR 241 FROM JUST ... | AL / Franklin |
$319,306
|
Total # Projects: | 21 |
Total # Contracts: | 10 |
Total $ Projects: | $73,751,549 |
Total $ Contracts: | $67,562,351 |
Congressmembers
- Sen. Richard C. Shelby (R) See Campaign Finances
- Sen. Jeff Sessions (R) See Campaign Finances
- Rep. Robert B. Aderholt (R) See Campaign Finances
Collaborate
These news organizations have followed up and written stories using this database:
- PBS NewsHour/Patchwork Nation analyzed how transportation stimulus funds were distributed across communities.
Add yourself to this list: News organizations are welcome to use data here in their own stories. Please credit ProPublica for providing the data. If you have a good story to share or collaborate on, contact Senior Editor Tom Detzel
Questions? Tips?
About This Data
Note: To build this database, ProPublica obtained two sets of records from the U.S. Department of Transportation. We cleaned it to remove duplicates and other discrepancies, but it may have mistakes we didn't catch. If you find one, please let us know and include any information that may help us verify the correction. Also, the federal data is based on the states’ monthly reporting and may not be up-to-date.
First, we received an updated copy of the national database of stimulus road and bridge projects as of Sept. 25. Separately, we obtained data that states filed to the federal government as part of the stimulus legislation's reporting requirements. These data list which contractors had been awarded particular projects. We were able to trace more than 90 percent of the funds to individual counties. In a few other cases, projects are statewide and cannot be narrowed to county or serve multiple counties. We’ve indicated those cases in the data.
Wherever possible, we matched DOT projects to state recovery filings. They did not match in every instance. The DOT projects, which total $19 billion, include hundreds of projects not yet associated with a contractor. The contractors' data totals about $13 billion in obligated funds. In a few cases, state contractors did not match a DOT project. Some projects also have multiple contractors. When there is no matching contractor information for a project, searches and lists will return a blank.
We're trying to make this information as accurate as possible, so if you see something that needs to be corrected, please let us know.
Read more...
Here are our tips for running background checks on stimulus contractors.
All projects for AL-04. Not all projects have been awarded contracts.
Project Name | Contractor | County | Improvement Type | Amount |
---|---|---|---|---|
WIDENING & RESURFACING SR-1 (US-431) FROM NORTH END OF THE TENN. RIVER BRIDGE TO CR-5 (CATHEDRAL CAVERNS HWY) (Federal ID: 0001548) | WHITAKER CONTRACTING CORPORATION | Marshall | Pavement Improvement | $3,761,469 |
PLANE/RESURFACE SR-17 FROM 0.7 MILE NORTH CR-29 TO CR-30 IN SULLIGENT, FY2009 PHASE 2 (Federal ID: 0017528) | S.T. BUNN CONST. CO. INC. | Lamar | Pavement Improvement | $6,084,240 |
RESURFACING AND STRIPING SR-17 FROM LAMAR COUNTY LINE TO SR-4 (Federal ID: 0017529) | S.T. BUNN CONST. CO. INC. | Marion | Pavement Improvement | $1,785,816 |
RESURFACE SR-33 FROM SR-74 TO NORTH END OF SIPSEY RIVER BRIDGE (Federal ID: 0033502) | ROGERS GROUP, INC. | Winston | Pavement Improvement | $1,006,784 |
RESURFACING SR-69 FROM I-65 IN GOOD HOPE TO SR-3 (US-31) IN CULLMAN (Federal ID: 0069523) | GOOD HOPE CONTRACTING CO., INC. | Franklin | Pavement Improvement | $1,614,641 |
RESURFACE, STRIPING SR-75 FROM CR-363 (BROOKS LANE) IN ALLGOOD TO CR-58 (2ND ST) IN ONEONTA (Federal ID: 0075515) | WHITAKER CONTRACTING CORPORATION | Blount | Pavement Improvement | $1,783,600 |
RESURFACE SR-118 FROM 4TH STREET IN CARBON HILL TO CR-298 (RIPLEY LOOP ROAD) (Federal ID: 0118508) | APAC MID-SOUTH, INC. | Walker | Pavement Improvement | $1,478,967 |
RESURFACE SR-129 FROM SR-171 (US-43) TO CR-49 IN HUBBERTVILLE, 2009 PHASE II (Federal ID: 0129502) | S.T. BUNN CONST. CO. INC. | Fayette | Pavement Improvement | $1,635,520 |
RESURFACING AND STRIPING SR 241 FROM JUST SOUTH OF THE MARION COUNTY LINE TO SR 237 (Federal ID: 0241501) | APAC MID-SOUTH, INC. | Franklin | Pavement Improvement | $319,306 |
I-59 CONCRETE PAVE REHAB WITH UNBONDED OVERLAY FROM 0.6 MI SO OF ATTALLA NO CITY LIMITS AT NB STA 123+33.20 (MP183.811) TO END OF BR OVER CR-276 (STEPHEN GAP ROAD) AT NB STA 699+86.27 (MP 194.712) (Federal ID: I059342) | HINKLE CONTRACTING CO. | Etowah | Pavement Improvement | $48,092,008 |
WIDENING & RESURFACING SR-75 FROM 0.4 MILE NORTH CR-50 TO 0.2 MILE SOUTH SR-35. FY 2009 PHASE 2 RESURFACING PROGRAM (Federal ID: 0075516) | No Contractor | DeKalb | Pavement Improvement | $3,137,927 |
RESURFACING CR-49 & CR-20 FROM NORTHERN ROW OF LUXAPALLILA VALLEY RR TO SR-17 - LCP 38-10-08 (Federal ID: 3804200) | No Contractor | Lamar | Pavement Improvement | $265,000 |
RESURFACE SOUTH SENECA DRIVE FROM TRINITY TOWN LIMITS TO DEANNA BRIDGE HIGHWAY (STATE SUPPORT SERVICES) (Federal ID: 5218200) | No Contractor | Morgan | Other | $3,827 |
RESURFACE CR-161 (INDIAN HILLS ROAD) FROM LINCOYA CIRCLE TO CR-239 (BEN POOLE RD.) IN THE CITY OF DECATUR (STATE SUPPORT SERVICES) (Federal ID: 5222200) | No Contractor | Morgan | Other | $4,207 |
EXTEND BLACK CR PARKWAY, S TO STEELE STA RD, 4-LN (Federal ID: 8104600) | No Contractor | Etowah | Pavement Improvement | $2,133,433 |
RESURFACING CR-684 (8TH ST. SE) FROM 16TH AVE.TO POINT MALLARD DR. AND POINT MALLARD DR. TO POINT MALLARD CIRCLE IN THE CITY OF DECATUR (STATE SUPPORT SERVICES) (Federal ID: PE09913) | No Contractor | Morgan | Other | $21,510 |
RESURFACE AND STRIPE COUNTRY CLUB ROAD FROM SR-67 TO SOMERVILLE RD IN THE CITY OF DECATUR. (STATE SUPPORT SERVICES) (Federal ID: PE09914) | No Contractor | Morgan | Other | $7,761 |
RESURFACE AND STRIPE PORTIONS OF CR-41 (DANVILLE ROAD) FROM CR-191 (CHAPEL HILL RD.) TO 2ND ST. SW. IN THE CITY OF DECATUR (STATE SUPPORT SERVICES) (Federal ID: PE09915) | No Contractor | Morgan | Other | $19,188 |
SIDEWALKS ALONG ALABAMA AVE., 18TH STREET AND 19TH STREET IN THE CITY OF JASPER. THIS PROJECT IS LOCATED ON ALABAMA AVE., 18TH ST. AND 19TH ST. IN DOWNTOWN JASPER. (Federal ID: TE09902) | No Contractor | Walker | Transportation Enhancements | $391,520 |
SIDEWALKS ALONG PARRISH JASPER ROAD FROM FIRST STREET TO PARRISH ELEMENTARY SCHOOL IN THE TOWN OF PARRISH. THIS PROJECT IS LOCATED ALONG JASPER RD. IN THE OLD DOWNTOWN AREA OF PARRISH. (Federal ID: TE09923) | No Contractor | Walker | Transportation Enhancements | $330,220 |
U.S. 431 LANDSCAPING IMPROVEMENTS IN THE CITY OF GLENCOE. THIS PROJECT IS LOCATED ALONG U.S. HIGHWAY 431 FROM BANK STREET TO KEYSBURG ROAD IN THE CITY OF GLENCOE. (Federal ID: TE09924) | No Contractor | Etowah | Transportation Enhancements | $172,500 |