THE CONTRACTOR SHALL PROVIDE ALL RESOURCES (EXCEPT AS EXPRESSLY STATED IN THE CONTRACT AS FURNISHED BY THE GOVERNMENT) NECESSARY TO DELIVER AND PERFORM THE WORK IN ACCORDANCE WITH THE DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK AND DRAWINGS PROVIDED FOR THIS TASK ORDER, YOUR BASIC TERMS AND CONDITIONS, DRAWINGS, AND SPECIAL CONDITIONS PROVIDED WITH THIS TASK ORDER. THE WORK TO BE PERFORMED UNDER THIS PROJECT CONSIST OF PROVIDING THE LABOR, EQUIPMENT, TOOLS, AND MATERIALS NECESSARY TO COMPLETE THE CONSTRUCTION AND/OR REPAIR AND MODIFY OF ELECTRICAL UTILITY EQUIPMENT AT BUILDING 2311 AND EQUIPMENT UTILITY AND CONTROL FOR LOCK GATES AT BUILDING 2310. THE WORK ALSO INCLUDES THE PROCUREMENT AND INSTALLATION OF EQUIPMENT TO BE PROVIDED NEW BY THE CONTRACTOR AS INDICATED AND REQUIRED FOR THE PROVISION OF FULLY FUNCTION SYSTEMS. THE TYPES OF EQUIPMENT INCLUDE BUT ARE NOT LIMITED TO TRANSFORMERS, MOTOR CONTROL ENTERS, CABLES, SWITCHES, SWITCHBOARD CONTROL SYSTEMS, CONSOLES, LIGHTS, VALVES, NEW DUCTBANK, PIPING, ELECTRICAL CABINETS, CONCRETE, PAVEMENT AND DEMOLITION. MUCH OF THE WORK IS IN CONFINED SPACES. CONTRACTOR SHALL PERFORM ALL PARTIAL CONSTRUCTION AS SUGGESTED ON THE DRAWINGS TO ENSURE DOWN TIMES DOES NOT EXCEED THE TIME FRAME AS INDICATED ON DRAWING E-002. ALL TERMINATION ON MAIN CONTROL BOARD, CONSOLES, AND TESTING SHALL BE PERFORMED BY MANUFACTURER'S TECHNICIANS. "ELECTRICAL REPAIRS TO CANAL LOCK CONTROLS." REPLACE ALL EXISTING LIGHTS AND PARTIAL CONDUIT.
Total Committed
$370K
Product or Service Description
Miscellaneous Buildings Construction
Contracting Agency
Effective Date
June 19, 2019
Funding Department
NASA STENNIS SPACE CENTER
Type
Firm fixed price
Solicitation Procedure
Subject to multiple award fair opportunity
Extent Competed
Full and open competition after exclusion of sources
Recent Contract Actions
Contracts can have multiple “contract actions”: This is how agencies spend money for a specific purpose, adjust the amount committed or change the contract in a way that doesn’t affect the amount. That last scenario is usually indicated by a $0 action. If there is a contract action for a negative amount, it generally means the contract was adjusted or canceled.
Vendor | Description | Signed | Reason for Change | Amount Committed |
---|---|---|---|---|
HEALTHEON, INC. | COVID-19 SITE CLOSURE RESULTED IN RENTAL COSTS DURING CLOSURE AND TO INCORPORATE A REQUEST FOR EQUITABLE ADJUSTMENT. A1 FIREX PIPING REPLACEMENT AND RUN TANK PAINTING AT STENNIS SPACE CENTER, MS | Jan. 27, 2021 | Supplemental Agreement For Work Within Scope | $68,195 |
HEALTHEON, INC. | THE CONTRACTOR SHALL PROVIDE ALL RESOURCES (EXCEPT AS EXPRESSLY STATED IN THE CONTRACT AS FURNISHED BY THE GOVERNMENT) NECESSARY TO DELIVER AND PERFORM THE WORK IN ACCORDANCE WITH THE DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK AND DRAWINGS PROVIDED FOR THIS TASK ORDER, YOUR BASIC TERMS AND CONDITIONS, DRAWINGS, AND SPECIAL CONDITIONS PROVIDED WITH THIS TASK ORDER. THE WORK TO BE PERFORMED UNDER THIS PROJECT CONSIST OF PROVIDING THE LABOR, EQUIPMENT, TOOLS, AND MATERIALS NECESSARY TO COMPLETE THE CONSTRUCTION AND/OR REPAIR AND MODIFY OF ELECTRICAL UTILITY EQUIPMENT AT BUILDING 2311 AND EQUIPMENT UTILITY AND CONTROL FOR LOCK GATES AT BUILDING 2310. THE WORK ALSO INCLUDES THE PROCUREMENT AND INSTALLATION OF EQUIPMENT TO BE PROVIDED NEW BY THE CONTRACTOR AS INDICATED AND REQUIRED FOR THE PROVISION OF FULLY FUNCTION SYSTEMS. THE TYPES OF EQUIPMENT INCLUDE BUT ARE NOT LIMITED TO TRANSFORMERS, MOTOR CONTROL ENTERS, CABLES, SWITCHES, SWITCHBOARD CONTROL SYSTEMS, CONSOLES, LIGHTS, VALVES, NEW DUCTBANK, PIPING, ELECTRICAL CABINETS, CONCRETE, PAVEMENT AND DEMOLITION. MUCH OF THE WORK IS IN CONFINED SPACES. CONTRACTOR SHALL PERFORM ALL PARTIAL CONSTRUCTION AS SUGGESTED ON THE DRAWINGS TO ENSURE DOWN TIMES DOES NOT EXCEED THE TIME FRAME AS INDICATED ON DRAWING E-002. ALL TERMINATION ON MAIN CONTROL BOARD, CONSOLES, AND TESTING SHALL BE PERFORMED BY MANUFACTURER'S TECHNICIANS. "ELECTRICAL REPAIRS TO CANAL LOCK CONTROLS." REPLACE ALL EXISTING LIGHTS AND PARTIAL CONDUIT. | Sept. 24, 2020 | Supplemental Agreement For Work Within Scope | $11,099 |
HEALTHEON, INC. | HIGH VOLTAGE DUCT BANK REFURBISHMENT AT STENNIS SPACE CENTER, MS (B. 9101) | Sept. 24, 2020 | Supplemental Agreement For Work Within Scope | $64,400 |
HEALTHEON, INC. | WEST PARK SITE INFRASTRUCTURE UPGRADES. MOD INCORPORATES REQUEST FOR EQUITABLE ADJUSTMENT DUE COVID-19 RETURN TO SITE, INCREASING TOTAL CONTRACT $23,873. COMPLETION DATE EXTENDED TO NOVEMBER 4, 2020. | Aug. 31, 2020 | Supplemental Agreement For Work Within Scope | $23,837 |
HEALTHEON, INC. | WEST PARK SITE INFRASTRUCTURE UPGRADES. THE PURPOSE OF THIS MODIFICATION IS TO EXTEND THE COMPLETION DATE 15 DAYS TO AUGUST 15, 2020 TO EVALUATE DENIED ACCESS TO KSC IMPACTS CURRENTLY IN REVIEW. ALL OTHER TERMS AND CONDITIONS REMAIN THE SAME. | July 30, 2020 | Supplemental Agreement For Work Within Scope | $0 |
HEALTHEON, INC. | A1 FIREX PIPING REPLACEMENT AND RUN TANK PAINTING AT STENNIS SPACE CENTER, MS | July 9, 2020 | Supplemental Agreement For Work Within Scope | $188,235 |
HEALTHEON, INC. | WEST PARK SITE INFRASTRUCTURE UPGRADES. MODIFICATION EXTENDS COMPLETION DATE TO 7/31/2020 TO EVALUATE KENNEDY SPACE CENTER DENIED ACCESS IMPACTS CURRENTLY PENDING SUBMISSION. ALL OTHER TERMS AND CONDITIONS REMAIN THE SAME. | June 23, 2020 | Supplemental Agreement For Work Within Scope | $0 |
HEALTHEON, INC. | A1 FIREX PIPING REPLACEMENT AND RUN TANK PAINTING AT STENNIS SPACE CENTER, MS | June 9, 2020 | Supplemental Agreement For Work Within Scope | $14,036 |
HEALTHEON, INC. | THE CONTRACTOR SHALL PROVIDE ALL RESOURCES (EXCEPT AS EXPRESSLY STATED IN THE CONTRACT AS FURNISHED BY THE GOVERNMENT) NECESSARY TO DELIVER AND PERFORM THE WORK IN ACCORDANCE WITH THE DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK AND DRAWINGS PROVIDED FOR THIS TASK ORDER, YOUR BASIC TERMS AND CONDITIONS, DRAWINGS, AND SPECIAL CONDITIONS PROVIDED WITH THIS TASK ORDER. THE WORK TO BE PERFORMED UNDER THIS PROJECT CONSIST OF PROVIDING THE LABOR, EQUIPMENT, TOOLS, AND MATERIALS NECESSARY TO COMPLETE THE CONSTRUCTION AND/OR REPAIR AND MODIFY OF ELECTRICAL UTILITY EQUIPMENT AT BUILDING 2311 AND EQUIPMENT UTILITY AND CONTROL FOR LOCK GATES AT BUILDING 2310. THE WORK ALSO INCLUDES THE PROCUREMENT AND INSTALLATION OF EQUIPMENT TO BE PROVIDED NEW BY THE CONTRACTOR AS INDICATED AND REQUIRED FOR THE PROVISION OF FULLY FUNCTION SYSTEMS. THE TYPES OF EQUIPMENT INCLUDE BUT ARE NOT LIMITED TO TRANSFORMERS, MOTOR CONTROL ENTERS, CABLES, SWITCHES, SWITCHBOARD CONTROL SYSTEMS, CONSOLES, LIGHTS, VALVES, NEW DUCTBANK, PIPING, ELECTRICAL CABINETS, CONCRETE, PAVEMENT AND DEMOLITION. MUCH OF THE WORK IS IN CONFINED SPACES. CONTRACTOR SHALL PERFORM ALL PARTIAL CONSTRUCTION AS SUGGESTED ON THE DRAWINGS TO ENSURE DOWN TIMES DOES NOT EXCEED THE TIME FRAME AS INDICATED ON DRAWING E-002. ALL TERMINATION ON MAIN CONTROL BOARD, CONSOLES, AND TESTING SHALL BE PERFORMED BY MANUFACTURER'S TECHNICIANS. "ELECTRICAL REPAIRS TO CANAL LOCK CONTROLS." REPLACE ALL EXISTING LIGHTS AND PARTIAL CONDUIT. | May 29, 2020 | Supplemental Agreement For Work Within Scope | $0 |
HEALTHEON, INC. | A1 FIREX PIPING REPLACEMENT AND RUN TANK PAINTING AT STENNIS SPACE CENTER, MS | April 8, 2020 | Supplemental Agreement For Work Within Scope | $0 |
HEALTHEON, INC. | THE CONTRACTOR SHALL PROVIDE ALL RESOURCES (EXCEPT AS EXPRESSLY STATED IN THE CONTRACT AS FURNISHED BY THE GOVERNMENT) NECESSARY TO DELIVER AND PERFORM THE WORK IN ACCORDANCE WITH THE DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK AND DRAWINGS PROVIDED FOR THIS TASK ORDER, YOUR BASIC TERMS AND CONDITIONS, DRAWINGS, AND SPECIAL CONDITIONS PROVIDED WITH THIS TASK ORDER. THE WORK TO BE PERFORMED UNDER THIS PROJECT CONSIST OF PROVIDING THE LABOR, EQUIPMENT, TOOLS, AND MATERIALS NECESSARY TO COMPLETE THE CONSTRUCTION AND/OR REPAIR AND MODIFY OF ELECTRICAL UTILITY EQUIPMENT AT BUILDING 2311 AND EQUIPMENT UTILITY AND CONTROL FOR LOCK GATES AT BUILDING 2310. THE WORK ALSO INCLUDES THE PROCUREMENT AND INSTALLATION OF EQUIPMENT TO BE PROVIDED NEW BY THE CONTRACTOR AS INDICATED AND REQUIRED FOR THE PROVISION OF FULLY FUNCTION SYSTEMS. THE TYPES OF EQUIPMENT INCLUDE BUT ARE NOT LIMITED TO TRANSFORMERS, MOTOR CONTROL ENTERS, CABLES, SWITCHES, SWITCHBOARD CONTROL SYSTEMS, CONSOLES, LIGHTS, VALVES, NEW DUCTBANK, PIPING, ELECTRICAL CABINETS, CONCRETE, PAVEMENT AND DEMOLITION. MUCH OF THE WORK IS IN CONFINED SPACES. CONTRACTOR SHALL PERFORM ALL PARTIAL CONSTRUCTION AS SUGGESTED ON THE DRAWINGS TO ENSURE DOWN TIMES DOES NOT EXCEED THE TIME FRAME AS INDICATED ON DRAWING E-002. ALL TERMINATION ON MAIN CONTROL BOARD, CONSOLES, AND TESTING SHALL BE PERFORMED BY MANUFACTURER'S TECHNICIANS. "ELECTRICAL REPAIRS TO CANAL LOCK CONTROLS." REPLACE ALL EXISTING LIGHTS AND PARTIAL CONDUIT. | March 27, 2020 | Supplemental Agreement For Work Within Scope | $0 |
About this data
This data comes from the Federal Procurement Data System, which includes all contracts worth $10,000 or more. We look at all contracts that are tagged with the procurement code for COVID-19 or otherwise started in 2020 and contain “COVID-19” in the description. Department of Defense contracting data is subject to a 90-day delay before it appears in the data.