Note: For some programs where states do not report where money will be distributed across the state, we do not have the allocation for individual counties. Those programs include: Medicaid, unemployment benefits and food stamps. Those amounts are included in the totals for where the state agency receiving that money is located.
Amount refers to both the amount of stimulus funding going toward the project and the face value of the loan.
Recipient | Amount | Description | Federal Dept./Agency | Date |
---|---|---|---|---|
PRECISION ENVIRONMENTAL COMPANY | $247,175 |
The work includes demolition, minor asbestos abatement, minor architectural repairs, new steel storage sheds, roofing, HVAC renovation and new construction, HVAC controls, CCTV site security system, AT/FP fencing system, site lighting, electrical retrofit
This spending item is part of a $3,533,376 allocation.
See details
|
Navy, Department of | 6/18/2009 |
ENERGY FOCUS, INC. | $224,515 |
Provide engineering, administrative and logistic support to Naval Surface Warfare Center for solid state lighting as part of the Fleet Readiness and Development Project.
This spending item is part of a $250,000 allocation.
See details
|
Navy, Department of | 9/11/2009 |
FOWLER ELECTRIC CO. | $197,204 |
The work includes demolition, minor asbestos abatement, minor architectural repairs, new steel storage sheds, roofing, HVAC renovation and new construction, HVAC controls, CCTV site security system, AT/FP fencing system, site lighting, electrical retrofit
This spending item is part of a $3,533,376 allocation.
See details
|
Navy, Department of | 6/18/2009 |
Lorad, LLC | $185,276 |
NAVFAC Atlantic issued this contract to install Photovoltaic (PV) systems and Building Integrated Photovoltaic (BIPV) systems on building rooftops, carports and ground-mounted PV arrays at various Naval Facilities Engineering Commands (FEC) for non-grid t
This spending item is part of a $66,434,472 allocation.
See details
|
Naval Facilities Engineering Command | 6/29/2009 |
FOWLER ELECTRIC CO. | $153,224 |
The primary objective of the work under this project is restoration and modernization of the existing facilities for improved efficiency and morale. A total of 375 days has been allocated for the completion of this project - 90 days for the design and 27
This spending item is part of a $3,044,499 allocation.
See details
|
Navy, Department of | 4/07/2009 |
ARISE SCAFFOLDING & EQUIPMENT, INC. | $63,000 |
RECOVERYPROJECT#::SD1018M::RP# REPAIR RECRUIT UNDERWATER SURVIVAL FACILITY, MARINE CORPS RECRUIT DEPOT, SAN DIEGO, CA
This spending item is part of a $1,099,119 allocation.
See details
|
Navy, Department of | 9/24/2009 |
Synecky Construction Inc | $62,000 |
The primary objective of the work under this project is restoration and modernization of the existing facilities for improved efficiency and morale. A total of 375 days has been allocated for the completion of this project - 90 days for the design and 27
This spending item is part of a $3,044,499 allocation.
See details
|
Navy, Department of | 4/07/2009 |