Sherman County, Ore., funds by U.S. Army Corps of Engineers
Listing $11,345,279.74 in stimulus funds from U.S. Army Corps of Engineers for Sherman
Note: For some programs where states do not report where money will be distributed across the state, we do not have the allocation for individual counties. Those programs include: Medicaid, unemployment benefits and food stamps. Those amounts are included in the totals for where the state agency receiving that money is located.
Amount refers to both the amount of stimulus funding going toward the project and the face value of the loan.
Recipient | Amount | Description | Federal Dept./Agency | Date |
---|---|---|---|---|
SLAYDEN CONSTRUCTION GROUP, INC. | $3,840,935 |
Demo fish weirs, install new weirs, install new fill actuated fill gates, electrical upgrades, install new counting station, misc. metals, walkways and handrails
This spending item is part of a $4,583,419 allocation.
See details
|
U.S. Army Corps of Engineers - civil program financing only | 9/28/2009 |
KNIGHT CONST. & SUPPLY, INC. | $2,396,860 | Recovery Project #122744, John Day Dam Avian Predation Deterrent Array Phase II. Build (6)steel towers to carry over five miles of synthetic lines crossing the spillway area of the dam to successfully deter predatory birds from attacking fish smolt downst | U.S. Army Corps of Engineers - civil program financing only | 12/23/2009 |
SLAYDEN CONSTRUCTION GROUP, INC. | $1,485,886 |
Construction of a concrete spillway flow deflector at spillway no. 20 at the John Day Dam to reduce the effects of nitrogen narcosis in fish migrating downstream.
This spending item is part of a $2,348,968 allocation.
See details
|
U.S. Army Corps of Engineers - civil program financing only | 9/29/2009 |
CP CONSTRUCTION LLC | $941,819 | Paving and Road Construction | U.S. Army Corps of Engineers - civil program financing only | 9/29/2009 |
GLEN/MAR CONSTRUCTION, INC. | $863,082 |
Construction of a concrete spillway flow deflector at spillway no. 20 at the John Day Dam to reduce the effects of nitrogen narcosis in fish migrating downstream.
This spending item is part of a $2,348,968 allocation.
See details
|
U.S. Army Corps of Engineers - civil program financing only | 9/29/2009 |
I N C A & CH2M HILL JOINT VENTURE | $717,164 | TAS:96 3134:: TAS Recovery Project #::138171 John Day Lock & Dam North Fishway Ladder Auziliary Water Supply System plans and specifications | U.S. Army Corps of Engineers - civil program financing only | 11/09/2009 |
GRANITE NORTHWEST, INC. | $618,939 |
LePage and Plymouth Park Paving at John Day Lock and Dam. Provide an asphalt concrete overlay for Plymouth Park campground and LePage Park campground.
This spending item is part of a $1,064,134 allocation.
See details
|
U.S. Army Corps of Engineers - civil program financing only | 9/29/2009 |
KONNOWAC, LLC | $406,284 |
LePage and Plymouth Park Paving at John Day Lock and Dam. Provide an asphalt concrete overlay for Plymouth Park campground and LePage Park campground.
This spending item is part of a $1,064,134 allocation.
See details
|
U.S. Army Corps of Engineers - civil program financing only | 9/29/2009 |
RICK'S TRANSFER SERVICE, INC. | $35,400 | Dive safety inspector John Dayflow deflector | U.S. Army Corps of Engineers - civil program financing only | 11/25/2009 |
LANPACIFIC, INC. | $25,095 |
LePage and Plymouth Park Paving at John Day Lock and Dam. Provide an asphalt concrete overlay for Plymouth Park campground and LePage Park campground.
This spending item is part of a $1,064,134 allocation.
See details
|
U.S. Army Corps of Engineers - civil program financing only | 9/29/2009 |
Baer Testing & Consulting, Inc. | $12,282 |
LePage and Plymouth Park Paving at John Day Lock and Dam. Provide an asphalt concrete overlay for Plymouth Park campground and LePage Park campground.
This spending item is part of a $1,064,134 allocation.
See details
|
U.S. Army Corps of Engineers - civil program financing only | 9/29/2009 |
A1 Straight Lines Striping Co | $1,534 |
LePage and Plymouth Park Paving at John Day Lock and Dam. Provide an asphalt concrete overlay for Plymouth Park campground and LePage Park campground.
This spending item is part of a $1,064,134 allocation.
See details
|
U.S. Army Corps of Engineers - civil program financing only | 9/29/2009 |