Douglas County, Neb., funds by General Services Administration
Listing $3,385,659.11 in stimulus funds from General Services Administration for Douglas
Note: For some programs where states do not report where money will be distributed across the state, we do not have the allocation for individual counties. Those programs include: Medicaid, unemployment benefits and food stamps. Those amounts are included in the totals for where the state agency receiving that money is located.
Amount refers to both the amount of stimulus funding going toward the project and the face value of the loan.
Recipient | Amount | Description | Federal Dept./Agency | Date |
---|---|---|---|---|
RL CAMPBELL MANAGEMENT SERVICES, INC. | $1,672,072 |
This is a modification to the ARRA ROOF REPLACEMENT, ROMAN L HRUSKA US COURTHOUSE,OMAHA, NE.
This spending item is part of a $2,541,585 allocation.
See details
|
Public Buildings Service | 7/28/2009 |
OMAHA PUBLIC POWER DISTRICT | $628,882 |
This is a modification to the ARRA ROOF REPLACEMENT, ROMAN L HRUSKA US COURTHOUSE,OMAHA, NE.
This spending item is part of a $2,541,585 allocation.
See details
|
Public Buildings Service | 7/28/2009 |
JOHNSON ROOFING & CONSTRUCTION, INC. | $240,631 |
This is a modification to the ARRA ROOF REPLACEMENT, ROMAN L HRUSKA US COURTHOUSE,OMAHA, NE.
This spending item is part of a $2,541,585 allocation.
See details
|
Public Buildings Service | 7/28/2009 |
THE WALDINGER CORPORATION | $230,376 |
The contract provides for preconstruction consultation services and construction services for Heating, Ventilation, & Air Conditioning (HVAC) upgrades to the Sioux City Courthouse and Federal Building. The project will design and install energy efficient
This spending item is part of a $2,193,941 allocation.
See details
|
Public Buildings Service | 2/22/2010 |
MORRISSEY ENGINEERING INC | $165,672 |
Update building systems based on an energy study prepared by Energy Management Control Engineers for the Robert Denny Buidling, Lincoln, Nebraska. The individual items studied (Energy Conservation Measure-1 througth Energy Conservation Measure-9) are sum
This spending item is part of a $247,742 allocation.
See details
|
Public Buildings Service | 10/15/2009 |
MORRISSEY ENGINEERING INC | $132,835 |
Provide Pre-Design, Design, Bidding, Construction and Post-Construction Services for the building system renovations located in the North Platte Federal Building.
This spending item is part of a $583,192 allocation.
See details
|
Public Buildings Service | 5/14/2009 |
GASTINGER AND WALKER ARCHITECTS INC | $114,708 | We provided Construction Manager as Agent services for this project in Omaha Nebraska. Project is completed. | Public Buildings Service | 8/17/2009 |
Johnson Hardware Co | $78,281 |
The contract award provides for preconstruction consultation services and construction services for additions to and the renovation of portions of the North Platte Federal Building in North Platte, NE. The physical scope of work includes a new building E
This spending item is part of a $5,319,809 allocation.
See details
|
Public Buildings Service | 6/26/2009 |
LEO A DALY COMPANY | $24,312 |
Updated the design of Heating, Ventilation, and Air Conditioning system that was originally developed by Alley Poyner Macchietto in cooperation with Leo A. Daly Engineers. Service to include all necessary revisions to the drawings and specifications based
This spending item is part of a $45,614 allocation.
See details
|
Public Buildings Service | 12/18/2009 |
BUILDING COMMISSIONING, L.L.C. | $19,000 |
The contract award provides for preconstruction consultation services and construction services for additions to and the renovation of portions of the North Platte Federal Building in North Platte, NE. The physical scope of work includes a new building E
This spending item is part of a $5,319,809 allocation.
See details
|
Public Buildings Service | 6/26/2009 |
PERFORMANCE ENGINEERING, INC. | $18,612 |
Provide Pre-Design, Design, Bidding, Construction and Post-Construction Services for the building system renovations located in the North Platte Federal Building.
This spending item is part of a $583,192 allocation.
See details
|
Public Buildings Service | 5/14/2009 |
LEO A DALY COMPANY | $16,802 |
Updated the design of HVAC system that was originally developed by Alley Poyner Macchietto in cooperation with Leo A. Daly Engineers. Service to include all necessary revisions to the drawings and specifications based on as-builts from Replace Perimeter H
This spending item is part of a $19,531 allocation.
See details
|
Public Buildings Service | 8/06/2009 |
PERFORMANCE ENGINEERING, INC. | $12,740 |
Update building systems based on an energy study prepared by Energy Management Control Engineers for the Robert Denny Buidling, Lincoln, Nebraska. The individual items studied (Energy Conservation Measure-1 througth Energy Conservation Measure-9) are sum
This spending item is part of a $247,742 allocation.
See details
|
Public Buildings Service | 10/15/2009 |
DRAKE-WILLIAMS STEEL, INC. | $9,925 |
The contract award provides for preconstruction consultation services and construction services for additions to and the renovation of portions of the North Platte Federal Building in North Platte, NE. The physical scope of work includes a new building E
This spending item is part of a $5,319,809 allocation.
See details
|
Public Buildings Service | 6/26/2009 |
MORRISSEY ENGINEERING INC | $9,148 |
Pre-design to install roof photovoltaic system.
This spending item is part of a $20,811 allocation.
See details
|
Public Buildings Service | 6/30/2009 |
ALLEY POYNER MACCHIETTO ARCHITECTURE, P.C. | $5,902 |
Pre-design to install roof photovoltaic system.
This spending item is part of a $20,811 allocation.
See details
|
Public Buildings Service | 6/30/2009 |
PERFORMANCE ENGINEERING, INC. | $5,761 |
Pre-design to install roof photovoltaic system.
This spending item is part of a $20,811 allocation.
See details
|
Public Buildings Service | 6/30/2009 |