Douglas County, Ore., funds by Interior, Department of
Listing $7,454,106.97 in stimulus funds from Interior, Department of for Douglas
Note: For some programs where states do not report where money will be distributed across the state, we do not have the allocation for individual counties. Those programs include: Medicaid, unemployment benefits and food stamps. Those amounts are included in the totals for where the state agency receiving that money is located.
Amount refers to both the amount of stimulus funding going toward the project and the face value of the loan.
Recipient | Amount | Description | Federal Dept./Agency | Date |
---|---|---|---|---|
CON-VEY/KEYSTONE, INC. | $2,197,300 | The overall purpose of this award is to perform High-Pressure Gate Modifications at Pinto Dam, located on the Columbia Basin Project in the State of Washington. AUS (Associated Underwater Services, Inc.) expects to successfully complete this project usin | Bureau of Reclamation | 4/19/2010 |
KENT CREEK QUARRY, INC. | $999,026 | crush and stockpile rock at designated stockpile areas | Bureau of Land Management | 11/23/2009 |
KENT CREEK QUARRY, INC. | $999,026 | roseburg crushed rock supply and delivery | Bureau of Land Management | 11/23/2009 |
ALL ROCK, LLC | $831,123 | haul rock to stockpile sites on blm roads | Bureau of Land Management | 11/24/2009 |
PARTNERSHIP FOR THE UMPQUA RIVERS INC | $415,000 | Fish, Wildlife and Plant Conservation Resource Management The objective of this project is to improve fish passage and other aquatic species access past culverts in streams in the Umpqua Basin on both public and private lands through the replacement of worn or otherwise undersized culverts. These repeplacement cul... Show more | Bureau of Land Management | 3/10/2010 |
WALKER'S EXCAVATION INC | $391,572 | Replacement of rusted out culverts, seeding , mulching and placement of aggregate surfacing on various roads in East Glendale area. | Bureau of Land Management | 8/26/2009 |
SUN, SAND & GRAVEL, INC. | $325,135 | Roseburg area vault toliets | Bureau of Land Management | 9/22/2009 |
COW CREEK BAND OF UMPQUA TRIBE OF INDIANS | $236,234 | Highway Planning and Construction ARRA IRR Rest Stop Phase 3 | Indian Affairs (Assistant Secretary) | 5/26/2010 |
ALL ROCK, LLC | $235,639 | DELIVERY OF CRUSHED ROCK TO GASSY CREEK ROAD | Bureau of Land Management | 3/04/2010 |
HUGHES BROS CONSTRUCTION CO | $234,100 | deliver aggregate to stockpile | Bureau of Land Management | 3/03/2010 |
NORTH RIVER BOATS INC | $151,032 | To manufacture 2 aluminum boats | Bureau of Reclamation | 9/24/2010 |
ALL ROCK, LLC | $139,328 | HAUL SUPPLY ROCK TO FOUR STOCK PILS SITES | Bureau of Land Management | 6/03/2010 |
ELK CREEK WATERSHED COUNCIL | $85,000 | Fish, Wildlife and Plant Conservation Resource Management This project will remove two (2) failing, undersized culverts and replace them with a concrete bridge. This will improve passage for anadromous fish, primarily coho salmon, and other aquatic species. | Bureau of Land Management | 3/16/2010 |
KUNERT ELECTRIC LLC | $69,196 | Install solar and microhyrdo systems at the Rogue River Ranch | Bureau of Land Management | 8/11/2010 |
PRO-TECT SEALCOATING | $65,506 | REPAIR AND SEAL PAVEMENT | Bureau of Land Management | 4/27/2010 |
NORTH RIVER BOATS INC | $46,898 | 2010 North River Seahawk OB Boat with Honda Motors & an EZ Loader Trailer. Fabrication and delivery. | Bureau of Reclamation | 4/07/2010 |
ROMTEC, INC. | $32,991 | RECOVERY VAULT TOILETS | Bureau of Land Management | 3/25/2010 |