Miradina Bazaar Cobblestone
Planned Start Month
March 2010
Estimated Cost
$556,070
Status
Canceled / Terminated
Province
Ghazni
Regional Command
RC-East
Project Description
Cobblestone the road that runs through Miradina Bazaar in Malistan District.
Project Goals
Improve overall road conditions of the busiest bazaar of the district while also employing local residents of nearby villages which will provide a source of income for people without jobs. The project will also improve drainage issues that occur during the rainy season that restrict accessiblity to the district center and shops in the bazaar and will also construct sidewalks in the bazaar area.
Results
Results unknown.
Updates
Aug 11 2009 awaiting funding Sep 15 2009 Awaiting funding. Oct 21 2009 Awaiting funding.