TF CREEK BULK DRAW, SSG Jones

Planned Start Month

Nov. 2011

Estimated Cost

$10,000

Status

Canceled / Terminated

Province

Paktiya

Regional Command

RC-East

Project Description

No project description provided.

Project Goals

Utilize monetary and other purchased incentives to enhance the standing of Coalition Forces

Results

Utilize monetary and other purchased incentives to enhance the standing of Coalition Forces and GIRoA in Paktya Province. Bulk CERP to support future Paktya operations. The goal of this procurement is to have a small amount of ready cash on hand to conduct high impact; low cost projects ISO the Afghan people of the province.

Updates

3 Nov PPO CERTS, PR&C, & ADR.

05 Nov 2011, submit for nomination

07 Nov 2011, Changed status to 'In Progress' Added STANFINS number Uploaded Funded PR&C 

20 Nov 2011, Uploaded drawing 1081 

12 Dec 2011, Closure Packet

TF Creek failed to terminate project, ODS is uploaded, project is now closed (04/16/12)