Culvert Replacement Jungal Bagh Farm

Planned Start Month

Dec. 2008

Estimated Cost

$10,894

Status

Completed

Province

Ghazni

Regional Command

RC-East

Project Description

This project will repair a culvert at Jungal Bagh that was severely damaged by an MRAP belonging to TX ADT. The road this culvert is on provides access to the Jungal Bagh Farm and will not be passable during the wet seasons without the culvert.

Project Goals

1) Access to Jungal Bagh Farm is re-established for vehicles (to include MRAPs).

2) The new Culvert is IED-resistant.

Results

This project repaired a culvert at Jungal Bagh that was severely damaged by an MRAP belonging to TX ADT 1.