Qalat City Hospital Plumbing Upgrade

Planned Start Month

April 2009

Estimated Cost

$8,710

Status

Completed

Province

Zabul

Regional Command

RC-South

Project Description

Upgrade Plumbing system at old Qalat City Hospital

Project Goals

Upgrade Plumbing system at old Qalat City Hospital ensuring a dependable water source and distribution system. Comments: Upgrade Plumbing system at old Qalat City Hospital ensuring a dependable water source and distribution system. 

Administrative closeout The outgoing unit remains pecuniary liable and administratively responsible for all negligent or illegal CERP operations conducted during their tour. This document does not relieve outgoing unit personnel of any pecuniary liability or administrative or disciplinary actions

Results

The contractor has finished all work and the hospital now has a working well and water tank for use.

Updates

The contractor has finished all work and the hospital now has a working well and water tank for use.
SOURCES

Illustrations: Sarah Way for ProPublica. Data: Assembled from several different Department of Defense databases by the Special Inspector General for Afghanistan Reconstruction and provided to ProPublica under a Freedom of Information Act Request.