Arapahoe County, Colo., funds by Interior, Department of
Listing $7,176,953.98 in stimulus funds from Interior, Department of for Arapahoe
Note: For some programs where states do not report where money will be distributed across the state, we do not have the allocation for individual counties. Those programs include: Medicaid, unemployment benefits and food stamps. Those amounts are included in the totals for where the state agency receiving that money is located.
Amount refers to both the amount of stimulus funding going toward the project and the face value of the loan.
Recipient | Amount | Description | Federal Dept./Agency | Date |
---|---|---|---|---|
BASEPOINT DESIGN CORPORATION | $1,098,194 |
Canal Inspections for Urbanized Areas - Canal Inspections for Urbanized Areas - onsite inspections to collect data associated with canals in proximity of urbanized areas, analysis of inspection data and follow up inspections as required
This spending item is part of a $3,254,393 allocation.
See details
|
Bureau of Reclamation | 12/29/2009 |
FRONT RANGE WIRELESS, INC. | $962,584 |
The purpose of this ESPC is to support and modernize BLM's overall facilities infrastructure, install Renewable Energy measures to lower greenhouse gases/carbon emissions and support BLM's overall mission. Ultimately, this ESPC will provide energy saving
This spending item is part of a $17,355,200 allocation.
See details
|
Bureau of Land Management | 3/31/2010 |
INNOVAR ENVIRONMENTAL INC | $847,167 |
Install safety closures at abandoned mines throughout the Mojave National Preserve to protect visitors and preserve resources.
This spending item is part of a $1,729,167 allocation.
See details
|
National Park Service | 4/16/2010 |
FRONT RANGE WIRELESS, INC. | $806,100 |
The purpose of this ESPC is to support and modernize BLM's overall facilities infrastructure, install Renewable Energy measures to lower greenhouse gases/carbon emissions and support BLM's overall mission. Ultimately, this ESPC will provide energy saving
This spending item is part of a $17,355,200 allocation.
See details
|
Bureau of Land Management | 3/31/2010 |
FRONT RANGE WIRELESS, INC. | $558,352 |
The purpose of this ESPC is to support and modernize BLM's overall facilities infrastructure, install Renewable Energy measures to lower greenhouse gases/carbon emissions and support BLM's overall mission. Ultimately, this ESPC will provide energy saving
This spending item is part of a $17,355,200 allocation.
See details
|
Bureau of Land Management | 3/31/2010 |
INNOVAR ENVIRONMENTAL INC | $488,244 |
Install safety closures in various Death Valley/Keane Wonder Mine areas' abandoned mines to protect visitors and preserve resources.
This spending item is part of a $588,881 allocation.
See details
|
National Park Service | 4/22/2010 |
BASEPOINT DESIGN CORPORATION | $454,061 |
Yuma Mesa Conduit Final Design - Design of sediment removal maholes, air vessels, and surge stands. Operation plan for overall system operation. Hydraulic, structural, and geotechnical engineering to design system modifications. Preparation of construc
This spending item is part of a $492,383 allocation.
See details
|
Bureau of Reclamation | 2/26/2010 |
W W WHEELER & ASSOCIATES INC | $355,556 |
Canal Inspections for Urbanized Areas - Canal Inspections for Urbanized Areas - onsite inspections to collect data associated with canals in proximity of urbanized areas, analysis of inspection data and follow up inspections as required
This spending item is part of a $3,254,393 allocation.
See details
|
Bureau of Reclamation | 12/29/2009 |
INNOVAR ENVIRONMENTAL INC | $327,980 |
Install safety closures at abandoned mines throughout the Mojave National Preserve to protect visitors and preserve resources.
This spending item is part of a $1,082,358 allocation.
See details
|
National Park Service | 4/01/2010 |
ECHO LABS LLC | $262,497 |
The purpose of this ESPC is to support and modernize BLM's overall facilities infrastructure, install Renewable Energy measures to lower greenhouse gases/carbon emissions and support BLM's overall mission. Ultimately, this ESPC will provide energy saving
This spending item is part of a $17,355,200 allocation.
See details
|
Bureau of Land Management | 3/31/2010 |
NORTHWEST FLORIDA WATER MANAGEMENT DISTRICT | $225,000 | Earthquake Hazards Reduction Program Grant awarded for the acquisition/processing of LiDAR data in Liberty County, Florida. | Geological Survey | 2/18/2010 |
Rocky Mountain Geothermal, Inc | $148,000 |
KANAB OFFICE BUILDING
This spending item is part of a $7,069,529 allocation.
See details
|
Bureau of Land Management | 9/16/2010 |
MERRICK & COMPANY | $133,251 |
This task order is for Planning, Acquisition, processing, and derivative products of lidar data to be collected at a nominal pulse spacing (NPS) of 2.0 meters. This task order is for lidar for three (3) areas in Florida: Lower Kissimmee River, Suwannee
This spending item is part of a $593,193 allocation.
See details
|
Geological Survey | 9/17/2010 |
J F SATO AND ASSOCIATES INC | $124,515 |
Planning, Design, and Engineering services for the Kanab Visitors Center.
This spending item is part of a $571,269 allocation.
See details
|
Bureau of Land Management | 8/31/2009 |
SDG, INC | $100,357 |
Farmington Title III Construction RFI responses.
This spending item is part of a $454,811 allocation.
See details
|
Bureau of Land Management | 5/03/2010 |
J F SATO AND ASSOCIATES INC | $58,253 | Bridge design for the replacement of the Cebolla Creek Bridge | Bureau of Land Management | 11/19/2009 |
J F SATO AND ASSOCIATES INC | $50,765 |
Planning, layout, and design of the Zapata Falls Campground expansion
This spending item is part of a $57,734 allocation.
See details
|
Bureau of Land Management | 11/12/2009 |
ISEC, INCORPORATED | $48,375 |
KANAB OFFICE BUILDING
This spending item is part of a $7,069,529 allocation.
See details
|
Bureau of Land Management | 9/16/2010 |
WOOLPERT, INC. | $33,000 |
This Bureau of Land Management (BLM), Colorado State Office, American Recovery and Reinvestment Act (ARRA) task will improve the quality for GCDB, LR2000 and MTP data. The result of this work will increase the spatial accuracy of GCDB, thereby giving BLM
This spending item is part of a $644,440 allocation.
See details
|
Bureau of Land Management | 3/15/2010 |
J F SATO AND ASSOCIATES INC | $30,744 |
Construction Administration, construction observation, and LEED Commissioning of the Kanab Office Building, Kanab, UT
This spending item is part of a $338,817 allocation.
See details
|
Bureau of Land Management | 8/27/2010 |
Ground Engineering Consultants, Inc. | $30,000 |
ROCKY MOUNTAIN ARSENAL DESIGN / BUILD AUTO TOUR ROUTE
This spending item is part of a $3,354,562 allocation.
See details
|
U.S. Fish and Wildlife Service | 8/12/2010 |
Sierra Contractors LLC | $14,927 |
ZAPATA FALLS CAMPGROUND
This spending item is part of a $476,816 allocation.
See details
|
U.S. Fish and Wildlife Service | 6/18/2010 |
INNOVAR ENVIRONMENTAL INC | $12,063 |
Install safety closures at abandoned mines to protect visitors and preserve resources.
This spending item is part of a $77,938 allocation.
See details
|
National Park Service | 4/08/2010 |
YEH AND ASSOCIATES, INC | $6,969 |
Planning, layout, and design of the Zapata Falls Campground expansion
This spending item is part of a $57,734 allocation.
See details
|
Bureau of Land Management | 11/12/2009 |
C3 LIMITED LIABILITY COMPANY | $0 |
CONSTRUCT INLET CANAL AT TOPOCK MARSH AT HAVASU NWR
This spending item is part of a $2,771,016 allocation.
See details
|
U.S. Fish and Wildlife Service | 3/29/2010 |
YEH AND ASSOCIATES, INC | $0 |
Bridge design for the replacement of the Cebolla Creek Bridge
This spending item is part of a $39,308 allocation.
See details
|
Bureau of Land Management | 11/19/2009 |