Farah - Pusht Rod Gravel Road
Planned Start Month
Aug. 2009
Estimated Cost
$1,243,800
Status
Completed
Province
Farah
Regional Command
Unknown
Project Description
16 km gravel road
Project Goals
The goal is to provide a gravel road from the Baghe Pul Bridge near Farah City to the District Center of Pusht Rod District. Comments: The existing road between Farah City and the Pusht Rod district center is in poor condition and impassable in some sections during rain.
Results
Project Complete IAW SOW
Updates
No updates provided.