« Money as a Bottomless Pit
Detailed Record
Kandahar City Potable Deep Water Wells
Planned Start Month
Oct. 2010
Estimated Cost
$4,625,842
Status
Completed
Province
Kandahar
Regional Command
RC-South
Project Description
No project description provided.
Project Goals
Kandahar City currently has limited water distribution system serviced by 15 shallow wells (50-125 meters), of which less than half are semi-functional. This system sporadically delivers potable to less than one third of the total population (estimated 850,000), with wells and pipe runs that cannot be effectively repaired in place. The Kandahar City water system is maintained by the Afghanistan Urban Water Supply and Sewerage Corporation (AUWSSC), a national body within the Ministry of Urban Development. At the provincial level, it is directed by the Mayor and Director of AUWSSC. Rehabilitation of the existing water system is outside of the current municipal capability. Current efforts from various International Government Organizations / Non-Government Organizations (IGOs/NGOs) have been made towards repairing the existing Kandahar City potable water supply system, but no new well sources have been created. Current hydro-geological data strongly indicates that deep wells are required to connect into a deep aquifer containing water untainted from city septic contamination. Access to drinking water is consistent with Islamic tenets and therefore these new wells will be protected by the citizens as a basic need for health and welfare. Delivery of additional potable water sources will serve as an obvious demonstration of e ffective National, Provincial, and District governance. Public availability of potable water will save lives and create civil stability. This project will consist of drilling three deep wells that will connect to a deep aquifer supply for Kandahar City, increasing the supply of potable water to the city. Well installation is to include well head size/location designs, and the associated local storage and system connection designs. Drilling contracts will be for an initial three (3) deep wells (1200-1500 FT) with bore holes of approximately 8 inch diameter or greater, and the immediate proximity installations required for connection of these sources to the existing Kandahar City supply system in accordance with a master plan.
Results
Results unknown.
Updates
08 FEB 2014 Uploaded base contract, all contract mods, and contract closure statement. This project is ready for closure, however, RC South is waiting on USACE to de-obligate the funds remaining on the MIPR. Once this is complete, closure documents will be uploaded, and project will be officially closed. 9 Oct. 13 uploaded Documents. 17JUN2013 Project transferred to GIRoA 21MAY2013 A transfer plan is developing IOT to transfer the wells in early JUN. (Infrastructure) 14MAY2013 ??% Cmplete, $2,912,429.18 remaining on account as of 2/15/2013. USACE refuses to provide updates and documents. 18FEB2011 Had to put .01 in the field of andquot;Amount of GIRoA funds for Project:andquot; in order for the project to be accepted as andquot;in progressandquot; CIDNE admin is aware of this. Line of accounting to USACE AEDS is MIPRDGFRC363AA Well Drilling contract solicitation issued o/a 06FEB, will close 08MAR. Well drilling work to commence o/a 07APR. Increase in public water source o/a 01JUN. This project was awarded for $4,625,842.21 16SEP2011 Updated estimated completion date per information received from MAJ Fagerquist, RC(S) Stab Div. 24SEP2012 Assuming RC(S) PM responsibility for this project. I am collecting information and background on this to develop a way forward. Steve Farkus 18OCT2012 The RC(S) infrastructure team has been in coordination with USACE. LTC Robert Bensburg has worked with USACE Program Manager Linda Murphy. USACE is currently looking for direction as where one of the well locations should be moved to. Steve Farkus 30OCT2012 USACE has all direction from RC(S). They must work with their contractor to get work at Well #3 restarted. 20NOV2012 46% USACE reported that Well #3 collapsed on the evening of 16NOV2012. This means that the excavation made by the drilling operation gave way and filled-in. USACE will be looking for specific guidance as to the exact relocation of Well #3. The modification for Well #2 has still not been signed by the USACE KO. Sf 10DEC2012 46% Complete. No water found at well #1 site. Solution is optional Well #4. Option cost is $860,456. Current year funds required. 17DEC2012 46% Complete. Suspension of Work is lifted on Well 2 and 3. Modifications in process to change location of well #2 and settle suspension. New CCD is anticipated at 18 APR 13 and BOD 18 JUN 13. 30JAN2013 Waiting on USACE to update. 14MAY2013 ??% Cmplete, $2,912,429.18 remaining on account as of 2/15/2013. USACE refuses to provide updates and documents.
SOURCES
Illustrations: Sarah Way for ProPublica. Data: Assembled from several different Department of Defense databases by the Special Inspector General for Afghanistan Reconstruction and provided to ProPublica under a Freedom of Information Act Request.